Talk:Romerike Tunnel/GA1
Appearance
GA Review
[edit]Article (edit | visual edit | history) · Article talk (edit | history) · Watch
Reviewer: ---Dough4872 16:51, 2 February 2010 (UTC)
- Is the cited information in the lead unique to the article? If not, then it does not need to be cited in the lead.
- "The leakages increased the cost of the tunnel from NOK 0.5 billion by an additional NOK 1.3 billion.": reword to indicate the specific amount the tunnel cost.
- Combine the sentences "In average 388 man-years were employed during construction. The work involved the removal of 1.62 million tonnes of rock."
- In the lead, you converted the length from meters to miles but in the body you converted the length from meters to feet. Can only one of these conversions be used for both?
I am placing the article on hold. ---Dough4872 16:51, 2 February 2010 (UTC)
- Thanks for the review. All changes have been made. Arsenikk (talk) 12:29, 3 February 2010 (UTC)
- I will pass the article. ---Dough4872 02:58, 4 February 2010 (UTC)