Green Line
Overview
StatusWinding down[1]
OwnerCalgary Transit
LocaleCalgary, Alberta, Canada
Termini
StationsPhase 1: 7
Stage 1: 15
Full vision: 29
Websitewww.calgary.ca/greenline
Service
TypeLight rail
SystemCTrain
Route number203
Operator(s)Calgary Transit
Depot(s)Highfield
Rolling stockCAF Urbos 100[2]
Daily ridershipPhase 1: 32,000[3]
Stage 1: 56,000–65,000[4]
Full vision: 140,000
History
Planned opening≈ 2031 (≈ 2031)[5]
Technical
Line lengthPhase 1: 10 kilometres (6.2 mi)
Stage 1: 20 kilometres (12 mi)
Full vision: 46 kilometres (29 mi)
Number of tracks2
CharacterAt-grade, elevated, underground, street running
Track gauge1,435 mm (4 ft 8+12 in)
ElectrificationOverhead lines, 750 V DC[6]
Operating speed80 kilometres per hour (50 mph)
Map diagram

Future extension
160 Avenue N
144 Avenue N
North Pointe
96 Avenue N
West Nose Creek
Beddington Trail NW
Beddington
64 Avenue N
Thorncliffe
40 Avenue N
28 Avenue N
16 Avenue N
9 Avenue N
Phase 2
Phase 1
Eau Claire
7 Avenue SW
Downtown Transit Mall
CTrain
Centre Street S
4 Street SE
Ramsay/Inglewood
26 Avenue SE
Highfield
Lynnwood/Millican
Ogden
South Hill
Quarry Park
Douglas Glen
Shepard
Future extension
Prestwick
McKenzie Towne
Auburn Bay/Mahogany
South Hospital
Seton

The Green Line, also known as Route 203, was a proposed expansion of the light rail (LRT) network in Calgary, Alberta, planned to run between Calgary's north-central and southeastern boundaries, connecting with the Red Line and Blue Line in the city's downtown. The Green Line would be the largest public infrastructure project in Calgary's history[7] and the first rail line in the city to operate low-floor trains if built.[8][9] If completed, the full vision of the Green Line would comprise 29 stations spanning 46 kilometres (29 mi), bringing the total number of CTrain stations in Calgary to 74.

Like the Red Line and Blue Line, the Green Line will be constructed in stages and phases. Stage one of construction features 15 stations (10 at-grade, 3 underground, 2 elevated). Phase 1, which is a portion of Stage 1, has been funded with three roughly equal contributions from the City of Calgary, the Government of Alberta, and the Government of Canada. Phase 1 will be 10 kilometres (6.2 mi) long and include 7 stations.

Major construction was planned to begin in early 2021 but was delayed to April 2022 after Alberta's United Conservative provincial government failed to contribute the province's pledged portion of the line's funding. The government rebuked the project as a "line to nowhere", asserting that the City of Calgary did not have "any credible plan" despite nearly four decades of research and planning.[10][11][12] This came after months of speculation from city officials, politicians, and journalists that the provincial government and others associated with the United Conservative Party[13][14][15][16] were attempting to stifle or cancel the Green Line.[17]

Due to the provincial government's actions, the City of Calgary temporarily paused the project's procurement though planning, pre-construction and public engagement continued through 2021.[12] Delays persisted until the project received final approval from Alberta's provincial government on July 7, 2021,[18] hours after Prime Minister Justin Trudeau met privately with Jason Kenney in Calgary. This meant the project had full approval from all three orders of government and Prime Minister Justin Trudeau stated "The money is there and the agreements are signed, so regardless of an election, the Green Line is going to go forward."[19]

Construction of the Green Line officially began in April 2022[20] with PCL Construction selected as the construction management contractor for utility relocation work.[21] The Green Line Board released the Request for Proposals (RFP) to select a proponent to construct phase one of stage one of construction, from Lynnwood/Millican to Eau Claire, on September 26, 2022. In April 2023, Green Line entered the Development Phase of the project and began the comprehensive design of the alignment.[22] On July 30, 2024, Calgary City Council approved a revised Green Line Phase 1 project scope, capital funding request, and delivery model, as recommended by the Green Line Board. The revised scope deferred the underground Centre Street Station for the future and shortened the line to end at Lynwood/Millican. It also moved the Maintenance and Storage Facility from Shepard to Highfield. Construction of the remainder of the Council-approved Phase 1 south to Shepard, and any future extensions north or south as outlined in the approved Stage 1 alignment plan, will proceed when additional funding is in place. This comes following increased cost pressures identified as the design was advanced. The revised Phase 1 scope from Eau Claire to Lynwood/Millican is anticpated to be completed in 2031.[23]

Description

[edit]
Diagram showing the full build-out/full future vision of the Green Line LRT project

The Green Line will be an urban and suburban light-rail line using low-floor trains, CAF Urbos 100, integrated as part of Calgary's CTrain system. Like the rest of Calgary's rail transit network, the Green Line will be entirely powered by wind power.[24] Operation of the line will be publicly funded by municipal taxation along with rider fares, and will be administered by Calgary Transit.

Generally, stations will be smaller and less elaborate than existing CTrain stations, due to the use of low-floor trains. In Phase 1, the southeast segment starting at Lynwood/Millican, will run as a light metro similar to the existing Red Line and Blue Line, with dedicated tracks, bells and gates on at-grade crossings and free standing stations. The track between 26 Avenue SE station and Ramsay/Inglewood station is then elevated on a guideway similar to the existing Sunalta station.

The line then heads underground with two abover ground and one underground station through the Beltline, the City Centre, and Eau Claire. The underground segment begins at a tunnel portal east of 4 Street SE. It will enter the Beltline in a shallow tunnel below 11 Avenue SE moving west before reorienting northward and moving under 2 Street SW.

The train then stops underground at 7 Avenue SW station in Calgary's urban core, providing direct transfer to the existing Red Line and Blue Line. The train will continue north, stopping underground at Eau Claire station in Eau Claire, exiting at a tunnel portal integrated into the Eau Claire Market, which will be redeveloped similar to the Central Library to accommodate the train.

Future phases of the approved Stage 1 plan include a bridge crossing the Bow River northwards, with two multi-use pathways, and connecting to Centre Street, north of the Centre Street Bridge. The train will then run northward in the centre two lanes of Centre Street in a dedicated right of way as an urban tramway, leaving two lanes for car traffic south of McKnight Boulevard and four lanes north of McKnight Boulevard. It also includes stations further south of Lynwood/Millican which are mostly at-grade stations with a section of elevated track crossing the intersection of Barlow Trail SE and 114 Avenue SE.

The train will run without gates, bells or fences on most at-grade crossings along Centre Street. The train will then continue northward; tracks will eventually enter into the median of Harvest Hills Boulevard, and the line will eventually span north of Stoney Trail into the exurban community of Keystone.[25][26]

Stations and route

[edit]

The full vision of the line will run from north-central to southeast Calgary on 46 kilometres (29 mi) of track and will feature 29 stations. This will bring the total number of CTrain stations in Calgary to 74. The planned Green Line corridor is currently served via three bus rapid transit (BRT) routes: Route 300 (operating the Calgary International Airport and downtown, primarily along Centre Street), Route 301 (between North Pointe and downtown)[27] and Route 302 (between Seton and downtown).[28] Like the Red Line and Blue Line, the Green Line will be built in stages. Stage one of construction will extend from 16 Avenue N at 16 Avenue N station, through downtown Calgary, to 126 Avenue SE at Shepard station.[29]

Stage 1 of construction will be built incrementally in smaller phases:[30]

Map showing the approved revised scope for phase 1 of Green Line LRT project going from Eau Claire to Lynnwood/Millican.
Map showing the approved revised scope for phase 1 of Green Line LRT project going from Eau Claire to Lynnwood/Millican
Key
Terminus (final build-out)
Terminus (phase one)
‡‡ Terminus (Stage one)

Green Line (Stage One)

[edit]
Station[31] Grade Opening Platform type Parking spaces[32] Approximate location
16 Avenue N‡‡ At-grade TBD Centre None On Centre Street N, between 16 Avenue and 14 Avenue N in Crescent Heights, on the southern edge of Tuxedo Park
9 Avenue N At-grade TBD Side None On Centre Street N, between 9 Avenue and 7 Avenue N in Crescent Heights, near Rotary Park
Eau Claire Underground 2031 Centre None Under Eau Claire, near the Bow River and Prince's Island Park, northwest of Riverfront Avenue and 2 Street SW
7 Avenue SW Underground 2031 Centre None Under 7 Avenue and 2 Street SW in Downtown Calgary, connection to the Red Line and Blue Line
Centre Street S Underground TBD Centre None Under 11 Avenue SE, south of the Calgary Tower in the Beltline
4 Street SE At-grade 2031 Centre None Under 11 Avenue SE, east of Olympic Way SE, at Stampede Park in the Beltline
Ramsay/Inglewood Elevated 2031 Side None Adjacent to the existing freight railroad tracks near 11 Avenue SE, elevated over 12 Street SE in Inglewood and Ramsay
26 Avenue SE Elevated 2031 Side None At 26 Avenue and 11 Street SE, elevated west of the Crossroads Market
Highfield At-grade 2031 Centre None Near Highfield Boulevard and Ogden Road SE, in Highfield, the city's oldest industrial area
Lynnwood/Millican At-grade 2031 Side 600 At Ogden Road and Millican Road SE adjacent to the Pop Davies Athletic Park in Lynnwood and Millican Estates
Ogden At-grade TBD Side None In the community of Ogden, at the Canadian Pacific Railway headquarters
South Hill At-grade TBD Side None Near Glenmore Trail and 24 Street SE adjacent to Riverbend
Quarry Park At-grade TBD Side None Near Quarry Park Boulevard, along 26 Street SE in Quarry Park
Douglas Glen At-grade TBD Side 600 Adjacent to 114 Avenue SE near Deerfoot Trail in Douglasdale/Douglasglen
Shepard‡‡ At-grade TBD Side 600 Near 126 Avenue SE, at the South Trail Crossing shopping centre

Planned northern expansion

[edit]
Station[31] Grade Opening Platform type Parking spaces[32] Approximate location
160 Avenue N† At-grade TBD Centre None On Centre Street N, at 160 Avenue N, in the outer suburban community of Keystone
144 Avenue N At-grade TBD Centre None On Centre Street N, at 144 Avenue N, north of Stoney Trail, in the community of Livingston
North Pointe At-grade TBD Centre TBD On Harvest Hills Boulevard, at Panamount Boulevard in Coventry Hills and Panorama Hills
96 Avenue N At-grade TBD Side TBD On Harvest Hills Boulevard, at 96 Avenue NE in Country Hills and Harvest Hills, future Calgary International Airport connection
Beddington At-grade TBD Side TBD On Centre Street N, at Beddington Boulevard in Beddington Heights
64 Avenue N At-grade TBD Side None On Centre Street N, at 64 Avenue N in Huntington Hills
Thorncliffe At-grade TBD Side None On Centre Street N, at McKnight Blvd in Thorncliffe
40 Avenue N At-grade TBD Side None On Centre Street N, at 40 Avenue N in Highland Park near the Greenview industrial area
28 Avenue N At-grade TBD Side None On Centre Street N, at 28 Avenue N in Tuxedo Park

Planned airport expansion

[edit]
Station[31] Grade Opening Platform type Parking spaces[32] Approximate location
88 Avenue NE† At-grade TBD TBD TBD At the proposed 88 Avenue NE Blue Line station
36 Street NE At-grade TBD TBD TBD On Airport Trail, in between 36 Street NE and Metis Trail NE in the Stoney 3/Jacksonport
Airport Terminal At-grade TBD TBD At YYC At Calgary International Airport, in between Parkade 1, Parkade 2, and the YYC International Terminal
Aero At-grade TBD TBD TBD On Aero Drive NE, in between Aero Link NE and Aero Way NE in the Aero Business Park
Auora At-grade TBD TBD TBD On 96 Avenue NE, at Harvest Hills Link NE in Stoney 2
96 Avenue N At-grade TBD Side TBD On Harvest Hills Boulevard, at 96 Avenue NE in Country Hills and Harvest Hills

Planned southeastern expansion

[edit]
Station[31] Grade Opening Platform type Parking spaces[32] Approximate location
Prestwick At-grade TBD Side TBD Adjacent to New Brighton at Prestwick Gate and 52 Street SE
McKenzie Towne At-grade TBD Side TBD In McKenzie Towne at McKenzie Towne Avenue and 52 Street SE
Auburn Bay / Mahogany At-grade TBD Side TBD In Auburn Bay and Mahogany, at Auburn Meadows Avenue and 52 Street SE, south of Stoney Trail
South Hospital At-grade TBD Side None At the South Health Campus, adjacent to Market Street SE
Seton† At-grade TBD Centre TBD At Seton Avenue and Seton Way SE, in the community of Seton

Expansion timeline and funding

[edit]

Though the alignment and general design of future expansions have been approved by the city council, the timeline and funding of future extensions has not yet been determined. Construction stage one builds the most complex and the most expensive segment of the line first - allowing incremental, relatively simple expansion of the line as funding becomes available. The full build-out of the line is estimated to require an additional CA$2–3 billion.

In 2019, several potential Stage 2 build-outs were evaluated for variable amounts of potential future funding. These were:[33]

  • $250–400 million:
  • $400–700 million:
  • $700 million–$1 billion:
    • North to 64 Avenue N or
    • South to Seton or
    • North to 40 Avenue N and south to Auburn Bay / Mahogany

Additional infrastructure

[edit]

When completed, Stage 1 of the Green Line will feature:

  • 40–45 low floor light rail trains, each 40 metres (130 ft) long
  • 20 kilometres (12 mi) of track
  • 15 stations (10 at-grade, 3 underground, 2 elevated)
  • 3 park and ride facilities with a total of 1,800 – 1,900 stalls (Lynnwood/Millican, Douglas Glen, and Shepard)
  • 1 kilometre (0.62 mi) of elevated track between Ramsay/Inglewood to 26 Avenue SE stations
  • 1 light rail vehicle (LRV) maintenance and storage facility, at Highfield[34]

When the full line is complete, it will also feature 12 bridges, 10 park and ride facilities (with 5,000 to 6,000 parking stalls), 10 tunnels (including the 2 km (1.2 mi)-long centre city tunnel from 2 St SW in Eau Claire to 11 Av SE in Victoria Park), a bridge connecting Eau Claire to Centre Street North, and 2 LRV maintenance and storage facilities (at Shepard and 96 Avenue N).[35][25]

Impact

[edit]

When the full vision is completed, from 160 Ave N to Seton, it's expected that 140,000 people will ride the Green Line every day. Stage 1 of construction is expected to have a daily ridership of 65,000 people. The city plans on creating many high density transit oriented development along the line once it is complete similar to how some areas around the existing C-Train lines have been redeveloped. The line will reduce travel times for existing north-central BRT and southeast BRT riders by an average of 25 minutes.[29]

The project is part of the cities plan to reduce emissions and meet Canada's Paris Agreement targets. Like the current C-Train Lines, the Green Line will be entirely powered by wind generated electricity and is expected to reduce greenhouse gas emissions by 67,000 tonnes of carbon dioxide per year, equivalent to 14,200 fewer vehicles on Calgary's roadways.[36][37]

Deerfoot Trail is currently the primary transportation route from north-central to southeast Calgary. It is the busiest freeway in Alberta, and suffers from chronic congestion. Calgarians spent an average of 15.7 hours in peak hour congestion in 2016.[38] The Green Line alignment runs roughly parallel to Deerfoot Trail and when finished will provide a competitive alternative to driving on the freeway resulting in an improved quality of life for Calgarians and reduced congestion on Deerfoot and its connecting roads.[37]

Anticipated Ridership

[edit]
Stations[39] 2028 2048
Eau Claire 6,500 9,200
7 Avenue SW 22,600 34,600
Centre Street S 3,400 5,400
4 Street SE 1,800 6,500
Ramsay/Inglewood 2,900 4,900
26 Avenue S 700 1,700
Highfield 1,000 1,600
Lynnwood/Millican 1,100 1,400
Ogden 1,300 2,000
South Hill 2,100 3,200
Quarry Park 900 2,100
Douglas Glen 2,900 3,100
Shepard 11,400 15,200

History

[edit]

Early history

[edit]

Trams ran on the surface of Centre Street for 41 years, from 1909 to 1950.[40] The Green Line will restore the historic alignment of Calgary's trams, running trains on the surface of Centre Street as well.

The Green Line was first envisioned in 1983, two years after Calgary's first LRT line opened.[41] As early as 1986, the communities of McKenzie Towne, New Brighton and Copperfield had set aside land along 52 Street SE for the future line. In 1987, the city then conducted the Southeast Mass Transit Corridor Study and concluded that southeast Calgary would one day require a dedicated light rail line.[42]

Original proposal

[edit]

In 2010, the city anticipated that the Green Line would be required before Calgary's population reached 1.25 million, though the city surpassed that population just 5 years later.[43] Chronic congestion on Deerfoot Trail is partly attributed to the failure to construct the Green Line before the 1.25 million population target.[44]

In 2011, the city began considering three possible alignments for the north-central leg of the Green Line: along Nose Creek adjacent to Deerfoot Trail, on Edmonton Trail, or on Centre Street. After engagement with the public, the city selected Centre Street as the preferred alignment.[citation needed]

In 2012, the Green Line was proposed as two separate new lines — one from downtown to north central and one from downtown to the southeast.[45] The division of the line was rejected by council.[46] Through 2016, $101 million had been spent on right-of-way acquisition and preliminary studies.[47]

In May 2017, the city revealed the line's suggested alignment and announced it would be built in stages due to the unexpectedly high costs of certain design choices.[48] Although the original estimate for the entire 28-station Green Line was $4.5 billion,[49] the cost of stage one alone, including the $1.95 billion cost of the centre city tunnel,[50] was estimated at $4.65 billion.[48]

Funding and alignment changes

[edit]

In 2015, the Government of Canada announced that it would invest a historic $1.53 billion in the Green Line, the single largest federal investment for an infrastructure project in Alberta.[51] In early 2019, Alberta's NDP provincial government committed $1.53 billion in funding paid for by the provincial carbon tax.[52] Over time, the City of Calgary set aside funding for the Green Line and has designated a $1.53 billion investment in the project. The Green Line is funded by three roughly equal contributions from all three orders of government.

In late 2019, after the 2019 Alberta General Election, the newly elected United Conservative provincial government cut the Green Line's budget by 86 percent[16] and passed legislation allowing their government to terminate their contribution "without cause" and with only 90 days notice.[53] This move complicated the city's ability to move forward with the project, hindered the city's access to the federal government's investment and raised uncertainty among potential procurement bidders.

On May 12, 2020, the city announced changes to the alignment of the line to keep the project within budget. The revised alignment replaced the deep-earth tunnel under the Bow River with an elevated guideway over the east end of Prince's Island Park. The elimination of the tunnel under the river significantly reduces construction cost and risk.

The changes also brought the line to the surface between 9 Avenue N and 16 Avenue N, running along the two centre lanes of Centre Street in a dedicated right of way. The Green Line north of 16 Avenue N has been planned as a surface running train since the city's 2017 recommendations. The changes also included the addition of 9 Avenue N station in Crescent Heights, increasing the number of stations in stage one of construction to 15, and bringing the total number of stations to 29. Eau Claire station and 4 Street SE station were moved from being at-grade to underground and the Beltline section of the line was moved one block north to run under 11 Avenue South, rather than under 12 Avenue S as initially recommended.

The plan for a tunnel under the intersection of Barlow Trail and 114 Avenue SE was scrapped in favour of an elevated guideway over the intersection, and the park and ride at Shepard station was revised from a parkade to a surface parking lot.[54][55]

On July 30, 2024, the city decided on changes to the phase 1 alignment to address the impact of cost overruns. The revised phase 1 alignment runs from Eau Claire but terminates at Lynnwood/Millican instead of Shepard. The new alignment also moves 4 Street SE from underground to at-grade to better integrate with planned future passenger rail and the planned "Grand Central Station", and moves the Maintenance and Storage Facility to Highfield Station instead of Shepard. The change also includes the deferral of Centre Street S to a future phase in order to minimize cost overruns.[56]

Opposition

[edit]

As the project's approval was looming in early 2020, a group of business people, some with ties to the United Conservative Party,[13] organized an invite only event at the Calgary Petroleum Club with city officials.[57] Despite speculation that the group's objective was to cancel the project despite its popular public support,[17][58][59] some attendees insisted otherwise.[60] One of the participants, oil industry executive and multimillionare Jim Gray, suggested the group was not opposed to the line but instead wanted to "de-risk" it.[60]

The group called for replacing half of the rail line with a bus, cancelling the downtown subway, and for the use of high-floor trains.[15] The group also funneled thousands of dollars into an online advertising campaign opposing the Green Line under the titles of "An Ad Hoc Committee of Calgary Citizens", "Rethink the Green Line", and "Green Line Done Right".

Rethink the Green Line has continued its campaign against the Green Line through 2024. The group has been noted for disseminating disinformation about the project and has made objectively incorrect claims in an attempt to garner opposition, such as the unfounded assertion that property taxes could increase by 90 percent if built.[61]

The group also published editorials in local newspapers, like the Calgary Herald, making a variety of dubious claims about the project and calling for its pause or cancellation. Additionally, the group hung anti-Green Line flyers in communities around the city and operated a website opposing the Green Line.[62] In December 2020, the United Conservative Minister of Transportation, Ric McIver, rebuked the Green Line saying in a statement that the train is a "line to nowhere"[11] and the city does not have "any credible plan".[63] After an additional 6 months of delays subsequent to McIver's statement saying the project's technical plans were inadequate, the province then announced the technical issues had been resolved despite no changes to the line's design or alignment.[64]

Despite the issue cited as the reason the province failed to contribute their pledged portion of the project's funding being resolved, the United Conservative provincial government then announced that it would continue withholding funding, the city needed to produce a new business case for the line, and it would be investing in the widening of Deerfoot Trail.[64][65] The Alberta provincial government has also retained legislation allowing them to revoke their contribution with only 90 days notice. Officials say this move complicates the project's procurement, increased the project's overall cost by millions of dollars and delayed the project by one year.[14] Despite these actions, the provincial government maintains publicly that they support the idea of the Green Line.[66][10]

On July 7, 2021, Prime Minister Justin Trudeau met privately with then-Alberta Premier Jason Kenney at the Fairmount Palliser Hotel in downtown Calgary. Less than three hours later, the Alberta Government announced it had approved the Green Line without modifications and would contribute their pledged portion of the line's funding.[18] After over a year of delays inflicted by the provincial government, Prime Minister Justin Trudeau, Mayor Naheed Nenshi, members of council, and various other stakeholders gathered at the Oliver Bowen Light Rail Maintenance Facility in Calgary to announce the Green Line would continue as planned. Jason Kenney declined to attend the announcement and sent no provincial representatives.[67]

Alberta's current premier, Danielle Smith, called the Green Line a "catastrophically bad decision", a "fantasy", and an "excessively expensive line that goes nowhere and never will". Danielle Smith also asserted that the Green Line is "of no real use to anyone", praised the organized effort to stifle or cancel the Green Line, and called for replacing half of the rail line with a bus.[68]

Approval and public opinion

[edit]

On June 16, 2020, council voted 14 to 1 to approve construction Stage 1 of the Green Line despite vocal opposition from a small group of wealthy and influential businesspeople.[23] The project received final approval from all three orders of government on July 7, 2021.[18] Several polls conducted in 2020 and 2021 have suggested that the project has popular public support. A poll conducted in June 2020 found 68.7 percent of Calgarians in support of the project with its updated 2020 alignment.[17] According to a 2021 survey conducted by the City of Calgary, 90 percent of respondents said the Green Line is important to the future of the city and 89 percent said it is an important addition to the city's transportation network.

The CA$5.5 billion cost of Stage 1 will be shared in roughly equal portions between the federal government, provincial government, and the City of Calgary.[69][70] On July 10, 2021, Prime Minister Justin Trudeau said "The money is there and the agreements are signed, so regardless of an election, the Green Line is going to go forward."[19]

Construction

[edit]

The City of Calgary began early works construction in 2017 with utility relocation and environmental redemption projects along the alignment of the line and spent over $500 million.[71] In November 2021, Construcciones y Auxiliar de Ferrocarriles (CAF) was awarded the contract to supply Green Line's new fleet of low floor trains.[9]

Construction on the Green Line officially began in April 2022[20] with PCL Construction selected as the construction management contractor working on deep utility relocations to prepare the Downtown and Beltline alignment areas for tunneling.[21] The Green Line Board released the Request for Proposals (RFP) to select a proponent to construct phase one of stage one of construction, from Shepard to Eau Claire, on September 26, 2022.

The City announced the selection of Bow Transit Connectors (a joint venture between Barnard Constructors of Canada, LP and Flatiron Constructors Canada Ltd) to build phase one of the line on April 29, 2023.[7] On June 5, 2023, Green Line selected Graham Construction to construct the 78 Avenue SE Grade Separation and Ogden Pedestrian Tunnel Project (“78 Avenue Project”) to prepare the area around the future Ogden Station.

Phase 1 of construction is expected to be completed approximately in 2031.[23]

Despite spending billions on feasibility studies and preparation, the City voted to wind down the Green Line, as of September 17, 2024.[72] However, Calgary and provincial government agree to build southeast section of Green Line, reviving five cancelled stops as of 10 October 2024. [73]

On October 30, 2024, Green Line CEO Darshpreet Bhatti shared with Calgary City Council during an update on the wind down that he was transitioning out of the role. [74]

References

[edit]
  1. ^ Markusoff, Jason (September 19, 2024). "Council declares Green Line dead, but Danielle Smith thinks her study can revive it". CBC News. Retrieved September 19, 2024.
  2. ^ "LRV CALGARY". LRVs and tram-trains. Retrieved June 15, 2024.
  3. ^ "FAQs and resources". Green Line LRT. Retrieved August 4, 2024.
  4. ^ "Update to the 2020 Business Case(2021)" (PDF). FAQs and resources. Retrieved June 15, 2024.
  5. ^ "When will the Green Line LRT open?". FAQs and resources. Retrieved June 15, 2024.
  6. ^ "SD160 Light Rail Vehicle: Calgary, Canada" (PDF). Siemens Transportation Systems, Inc. 2007. Archived from the original (PDF) on October 26, 2010. Retrieved January 23, 2011. Catenary supply voltage: 600 Vdc
  7. ^ a b Krause, Darren (June 17, 2020). "Province to review Calgary Green Line plan: McIver letter". LiveWire Calgary. Retrieved September 21, 2020.
  8. ^ "Green Line Stage One". Engage. Retrieved September 21, 2020.
  9. ^ a b "Experience the LRV ride | Green Line LRT". www.calgary.ca. Retrieved September 26, 2022.
  10. ^ a b "Green Line construction in 2021 now a 'fantasy' as contract pause drags on, supporters say". Calgary Herald. Retrieved March 29, 2021.
  11. ^ a b "Nenshi says provincial 'foot-dragging' could delay Green Line work". Calgary Herald. Retrieved September 5, 2024.
  12. ^ a b "Green Line LRT procurement process stopped in its tracks due to provincial funding uncertainty". December 17, 2020.
  13. ^ a b "Group that wants pause on Green Line hosted private event with top city officials".
  14. ^ a b "'Get on with it': Nenshi says province is 'foot-dragging,' could add millions to Green Line costs". Calgary Herald. Retrieved March 25, 2021.
  15. ^ a b Krause, Darren (May 25, 2020). "Groups vie for footing in Calgary's Green Line debate". LiveWire Calgary. Retrieved June 23, 2020.
  16. ^ a b "Jason Kenney Cuts Green Line Budget 86%".
  17. ^ a b c "New poll shows most Calgarians are in support of Green Line plan". Global News. Retrieved June 23, 2020.
  18. ^ a b c "Elbow bumps all around: Trudeau meets face to face with Kenney and Nenshi in Calgary". Calgary Herald. Retrieved July 15, 2021.
  19. ^ a b "Sprawlcast: An interview with Prime Minister Justin Trudeau". The Sprawl. July 10, 2021. Retrieved July 15, 2021.
  20. ^ a b MacVicar, Adam (April 13, 2022). "Work begins to make way for Green Line LRT tunnel under downtown Calgary". Global News. Calgary, Alberta. Retrieved June 13, 2022.
  21. ^ a b "PCL begins Calgary's Green Line utility relocation - REMI Network". REMINET. Retrieved May 28, 2021.
  22. ^ "Green Line names Bow Transit Connectors as Development Partner". www.calgary.ca. Retrieved August 8, 2024.
  23. ^ a b c "FAQs and resources". Green Line LRT. Retrieved August 4, 2024.
  24. ^ "The City of Calgary: Investing in the Calgary Green Line". Retrieved September 5, 2024.
  25. ^ a b "Green Line - Segment 2 :: Green Line Stage One". Engage. Retrieved May 18, 2020.
  26. ^ "Green Line Long Term Vision Report" (PDF).
  27. ^ "BRT North/Downtown, Route 301" (PDF). Calgary Transit. Retrieved May 16, 2019.
  28. ^ "BRT Southeast, Route 302" (PDF). Calgary Transit. Retrieved May 16, 2019.
  29. ^ a b "Calgary Green Line Info graphics Place mat" (PDF). Retrieved September 5, 2024.
  30. ^ "Green Line LRT announces Phase 1 RFQ shortlist winners - constructconnect.com". Journal Of Commerce. August 1, 2022. Retrieved October 30, 2022.
  31. ^ a b c d "City of Calgary Route Ahead Plan (Updated May 2020)" (PDF). Retrieved September 5, 2024.
  32. ^ a b c d "Park & Ride Locations - Calgary Transit". www.calgarytransit.com. Retrieved February 2, 2018.
  33. ^ Hudes, Sammy (March 18, 2019). "Next Green Line phase might only extend north to 64th Avenue". Calgary Herald. Retrieved May 16, 2019.
  34. ^ "Highfield". Green Line LRT. Retrieved August 4, 2024.
  35. ^ "Alignment and Station Overview" (PDF). Green Line LRT Long Term Vision: 160 Avenue N to Seton (Report). City of Calgary. October 2017. Retrieved May 16, 2019.
  36. ^ "The City of Calgary: ADDRESSING CALGARY'S NEEDS WITH GREEN LINE LRT" (PDF). Retrieved September 5, 2024.
  37. ^ a b "City of Calgary: Investing in Calgary's Green Line LRT". Retrieved September 5, 2024.
  38. ^ "CBC: Deerfoot Trail congestion".
  39. ^ "List of stations | Green Line LRT". www.calgary.ca. Retrieved January 1, 2024.
  40. ^ "The City of Calgary's Transit History". The Gauntlet. May 10, 2018. Retrieved June 21, 2020.
  41. ^ Keating, Shane (September 20, 2019). "A (somewhat) Brief History of the Green Line". Shane Keating — Councillor Ward 12. Retrieved June 22, 2020.
  42. ^ "Southeast Mass Transit Corridor Study" (PDF). Retrieved September 5, 2024.
  43. ^ "Calgary's Population, 1958-2019 | Open Calgary". data.calgary.ca. Retrieved June 22, 2020.
  44. ^ Keating, Shane (February 24, 2017). "A Chat About Calgary Congestion". Shane Keating — Councillor Ward 12. Retrieved June 30, 2020.
  45. ^ Smith, Kevin (October 29, 2012). "Canada's light rail renaissance". International Railway Journal. Retrieved May 21, 2019.
  46. ^ "City council approves Green Line, with conditions to keep it on budget". Calgary Herald. Retrieved June 30, 2020.
  47. ^ Klingbeil, Annalise (May 16, 2017). "City has spent $101M on Green Line LRT so far, land acquisition going 'pretty smoothly'". Calgary Herald. Retrieved May 16, 2019.
  48. ^ a b Klingbeil, Annalise (May 16, 2017). "First phase of Green Line would cost $4.65 billion, run from Crescent Heights to Shepard". Calgary Herald. Retrieved May 16, 2019.
  49. ^ Howell, Trevor (February 13, 2017). "Green Line LRT to be phased in, won't reach transit-starved communities for years". Calgary Herald. Retrieved May 16, 2019.
  50. ^ Klingbeil, Annalise (November 2, 2016). "$1.95 billion underground tunnel for Green Line LRT recommended by city". Calgary Herald. Retrieved May 16, 2019.
  51. ^ "Tories announce $1.5B for Green Line LRT project". Calgary Herald. Retrieved March 25, 2021.
  52. ^ "Funding arrangement officially secured for first stage of Calgary Transit's Green Line". Calgary. January 30, 2019. Retrieved June 22, 2020.
  53. ^ "Proposed legislation allows UCP cabinet to kill Green Line funding with 90-day notice". Calgary Herald. Retrieved June 27, 2020.
  54. ^ "Green Line - Segment 1 :: Green Line Stage One". Engage. Retrieved September 9, 2020.
  55. ^ "Green Line - Segment 2 :: Green Line Stage One". Engage. Retrieved September 9, 2020.
  56. ^ "Green Line LRT moves forward with a revised Phase 1 project and capital request to address rising costs". Green Line LRT. Retrieved August 4, 2024.
  57. ^ "Green Line poll commissioned by group calling to 'de-risk' LRT tests support for 'alternative plan'". Calgary Herald. Retrieved June 23, 2020.
  58. ^ "Delay Green Line or risk 'economic catastrophe', business group tells council". Calgary Herald. Retrieved July 21, 2020.
  59. ^ "Calgary businessmen urge city to put the brakes on Green Line LRT". Calgary. June 26, 2019. Retrieved July 21, 2020.
  60. ^ a b "Green Line poll tests support for business group's 'alternative plan'". Calgary Sun. June 11, 2020. Retrieved June 23, 2020.
  61. ^ "Property taxes could increase ... and go as high as 90% to pay for the entire project". Facebook.
  62. ^ "Rethink the Green Line | Home". May 19, 2020. Archived from the original on May 19, 2020. Retrieved May 29, 2021.
  63. ^ "City asks to see provincial Green Line report after tense week for LRT project". Calgary Herald.
  64. ^ a b "UCP government wants a "business case" for Calgary's Green Line".
  65. ^ "P3 to expand Deerfoot Trail improvements". www.alberta.ca. Retrieved May 18, 2021.
  66. ^ Villani, Mark (December 17, 2020). "Green Line LRT procurement process stopped in its tracks due to provincial funding uncertainty". Calgary. Retrieved March 25, 2021.
  67. ^ "Trudeau, Nenshi announce final approval of Green Line".
  68. ^ "Smith: Calgary on cusp of catastrophic decision to OK Green Line to nowhere". calgaryherald. Retrieved November 4, 2022.
  69. ^ "Alberta pledges $1.53B for Green Line LRT". CBC News Calgary. July 6, 2017. Retrieved October 11, 2017.
  70. ^ "When will construction of the Green Line start? - 660 NEWS". www.660citynews.com. March 29, 2021. Retrieved April 11, 2021.
  71. ^ "Construction updates for Green Line". www.calgary.ca. Retrieved July 12, 2020.
  72. ^ "Project Update - September 17, 2024".
  73. ^ https://calgaryherald.com/news/local-news/calgary-alberta-agree-to-build-large-portion-southeast-green-line. {{cite web}}: Missing or empty |title= (help)
  74. ^ https://globalnews.ca/news/10838946/ceo-calgary-green-line-steps-down/. {{cite web}}: Missing or empty |title= (help)
[edit]
  • Green Line LRT Long Term Vision: 160 Avenue N to Seton, in twelve parts: