S/N | Station | Location | Capacity (MW) | Primary fuel |
---|---|---|---|---|
1 | TPS Jamshoro | Jamshoro, Sindh | 880 | RFO+gas |
2 | TPS Guddu (Units 5-10) | Guddu, Sindh | 600 | Gas |
3 | TPS Guddu (Units 11-13) | Guddu, Sindh | 415 | Gas |
4 | TPS Guddu (Units 14-16) | Guddu, Sindh | 747 | Gas |
5 | TPS Quetta | Quetta, Balochistan | 28 | Gas |
6 | TPS Muzaffargarh | Muzaffargarh, Punjab | 1,350 | Gas |
7 | TPS Nandipur | Gujranwala, Punjab | 567 | Gas |
8 | Lal Pir Power | Mehmood Kot, Punjab | 362 | RFO |
9 | Pak Gen. Power | Mehmood Kot, Punjab | 365 | RFO |
10 | Fauji Kabirwala | Kabirwala, Punjab | 170 | Gas |
11 | Hub Power | Hub, Balochistan | 1,292 | RFO |
12 | KAPCO | Kot Addu, Punjab | 1,600 | Gas |
13 | Kohinoor Energy Ltd | Lahore, Punjab | 131 | RFO |
14 | Rousch Power | Sidhnai, Punjab | 450 | Gas |
15 | Saba Power Company Ltd | Sheikhupura, Punjab | 136 | RFO |
16 | TNB Liberty Power | Daharki, Sindh | 235 | Gas |
17 | Uch Power | Murad Jamali, Balochistan | 586 | Gas |
18 | Attock Gen. | Attock Morgah, Punjab | 165 | RFO |
19 | Atlas Power | Sheikhupura, Punjab | 224 | RFO |
20 | Engro Power Gen. Qadirpur | Qadirpur, Sindh | 227 | Gas |
21 | Saif Power | Sahiwal, Punjab | 225 | Gas |
22 | Orient Power | Balloki, Punjab | 225 | Gas |
23 | Nishat Power | Qasur, Punjab | 202 | RFO |
24 | Nishat Chunian | Qasur, Punjab | 202 | RFO |
25 | Xenel Sapphire Electric | Muridke, Punjab | 235 | Gas |
26 | Halmore Power | Bhikki, Punjab | 225 | Gas |
27 | Narowal Energy | Narowal, Punjab | 214 | RFO |
28 | Liberty Power Tech. | Faisalabad, Punjab | 202 | RFO |
29 | Foundation Power | Daharki, Sindh | 179 | Gas |
30 | Uch-II Power | Murad Jamali, Balochistan | 404 | Low BTU gas |
31 | Sahiwal Coal Power Plant | Sahiwal, Punjab | 1,320 | Bituminous coal |
32 | QATPL (Bhikki) | Bhikki, Punjab | 1,180 | Regasified-LNG |
33 | NPPMCL (Haveli Bahadur Shah) | HBS, Jhang, Punjab | 1,230 | Regasified-LNG |
34 | NPPMCL (Balloki) | Balloki, Punjab | 1,223 | Regasified-LNG |
35 | Port Qasim Electric Power | Port Qasim, Sindh | 1,320 | Bituminous coal |
36 | China Power Hub | Lasbella, Balochistan | 1,320 | Bituminous coal |
37 | Engro Powergen Thar | Tharparkar, Sindh | 660 | Lignite (Thar coal) |
38 | Bin Qasim TPS-I | Karachi, Sindh | 840 | Dual |
39 | Bin Qasim TPS-II | Karachi, Sindh | 572 | Dual |
40 | Bin Qasim TPS-III | Karachi, Sindh | 942 | Regasified-LNG |
41 | Korangi Town GTPS-II | Karachi, Sindh | 107 | Gas |
42 | Site GTPS-II | Karachi, Sindh | 107 | Gas |
43 | Korangi CCPP | Karachi, Sindh | 248 | Gas |
44 | Gul Ahmed | Karachi, Sindh | 136 | RFO |
45 | Tapal Energy | Karachi, Sindh | 126 | RFO |
46 | SNPCL-I (IPP-2002) | Jamshoro, Sindh | 52 | Gas |
47 | SNPCL-II (IPP-2002) | Jamshoro, Sindh | 52 | Gas |
48 | Intl. Steel Limited (CPP) | Karachi, Sindh | 19 | Gas |
49 | Intl. Ind. Limited (CPP) | Karachi, Sindh | 4 | Gas |
50 | FFBL Power | Karachi, Sindh | 52 | Bituminous coal / lignite (Thar coal) |
51 | Lotte Chemicals | Karachi, Sindh | 14 | Gas |
52 | Lucky Cement | Lakki Marwat, KPK | 5 | Gas |
53 | Lucky Electric Power Co. Ltd | Bin Qasim, Sindh | 660 | Bituminous coal / lignite (Thar coal) |
54 | Punjab Thermal (PTPL) | Jhang, Punjab | 1,263 | Regasified-LNG |
55 | Thar Energy | Tharparkar, Sindh | 330 | Lignite (Thar coal) |
56 | Thar Coal Block-1 Power | Tharparkar, Sindh | 1,320 | Lignite (Thar coal) |
57 | ThalNova Power | Tharparkar, Sindh | 330 | Lignite (Thar coal) |
Under construction
[edit]S/N | Station | Location | Capacity (MW) | Primary Fuel | Status |
---|---|---|---|---|---|
1 | Coal Power Project, Jamshoro | Jamshoro, Sindh | 1,320 | Bituminous coal / lignite (Thar coal) |
First 660 MW unit is 91% completed[when?] and its expected COD was in November 2022.[3] |
Nuclear
[edit]In service
[edit]S/N | Station | Location | Capacity (MW) | Year in service |
---|---|---|---|---|
1 | (CHASNUPP-1) | Mianwali, Punjab | 325 | 2000 |
2 | (CHASNUPP-2) | Mianwali, Punjab | 325 | 2011 |
3 | (CHASNUPP-3) | Mianwali, Punjab | 340 | 2016 |
4 | (CHASNUPP-4) | Mianwali, Punjab | 340 | 2017 |
5 | (KANUPP-2) | Karachi, Sindh | 1,145 | 2021 |
6 | (KANUPP-3) | Karachi, Sindh | 1,145 | 2022 |
Under construction
[edit]S/N | Station | Location | Capacity (MW) | Status |
---|---|---|---|---|
1 | (CHASNUPP-5) | Mianwali, Punjab | 1,200 | Groundbreaking performed on July 14, 2023.[5] |
Hydro
[edit]In service
[edit]S/N | Station | Location | Type of power station | Capacity (MW) | In-service year |
---|---|---|---|---|---|
1 | Renala | Renala, Punjab | Run of canal | 1 | 1925 |
2 | Malakand / Jabban | Malakand, KPK | Run of river | 22 | 1935 |
3 | Rasul | Mandi Bahauddin, Punjab | Run of canal | 22 | 1952 |
4 | Dargai | Malakand, KPK | Run of canal | 20 | 1952 |
5 | Kurram Garhi | Kurram Garhi, KPK | Run of canal | 4 | 1958 |
6 | Chichonki Malian | Sheikhupura, Punjab | Run of canal | 13 | 1959 |
7 | Warsak | Peshawar, KPK | Run of river | 243 | 1960 |
8 | Shadiwal | Shadiwal Warriach, Punjab | Run of canal | 14 | 1961 |
9 | Nandipur | Gujranwala, Punjab | Run of canal | 14 | 1963 |
10 | Mangla | Mirpur, Azad Kashmir | Reservoir | 1,000 | 1967 |
11 | Chitral | Chitral, KPK | Run of canal | 1 | 1975 |
12 | Tarbela | Tarbela, KPK | Reservoir | 4,888 | 1977 |
13 | Chashma | Chashma, Punjab | Run of river | 184 | 2000 |
14 | Jagran | Neelum, Azad Kashmir | Hydro | 30 | 2000 |
15 | Ghazi-Barotha | Attock, Punjab | Run of river | 1,450 | 2003 |
16 | Malakand-III | Malakand, KPK | Run of river/canal | 84 | 2008 |
17 | Khan Khwar | Shangla, KPK | Reservoir | 72 | 2010 |
18 | Pehur | Swabi, KPK | Canal fall/run of river | 18 | 2010 |
19 | Jinnah | Jinnah Barrage, Punjab | Run of river | 96 | 2012 |
20 | Garam Chashma | Chitral, KPK | Hydro | 1 | 2012 |
21 | Allai Khwar | Mansehra, KPK | Reservoir | 121 | 2013 |
22 | Gomal Zam | South Waziristan | Reservoir | 17 | 2013 |
23 | New Bong Escape (Laraib Energy) |
Mirpur, Azad Kashmir | Hydro | 84 | 2013 |
24 | Duber Khwar | Kohistan, KPK | Reservoir | 130 | 2014 |
25 | Patrind Hydro | Muzaffarabad, Azad Kashmir | Run of river | 147 | 2017 |
26 | Golen Gol | Chitral, KPK | Run of river | 108 | 2018 |
27 | Neelum–Jhelum | Muzaffarabad, Azad Kashmir | Run of river | 969 | 2018 |
28 | Marala Hydro (PPDCL) | Sialkot, Punjab | Canal fall/run of river | 8 | 2018 |
29 | Gulpur Hydropower Plant, Barali | Kotli, Azad Kashmir | Run of river | 100 | 2020 |
30 | Daral Khwar | Swat District, KPK | Run of river | 37 | 2021 |
31 | Ranolia | Kohistan, KPK | High head | 17 | 2021 |
32 | Karot | Azad Kashmir / Punjab | Run of river | 720 | 2022 |
33 | Suki Kinari | Mansehra District, KPK | Run of river | 884 | 2024 |
Under construction
[edit]S/N | Station | Location | Capacity (MW) | Status |
---|---|---|---|---|
1 | Keyal Khwar | Lower Kohistan, Khyber Pakhtunkhwa | 128 | Under construction[7] |
2 | Dasu | Dasu Town | 4,320 | Under construction. Stage-I: 2,160 MW to be completed by April 2026.[8] |
3 | Tarbela 5th Ext. | Tarbela, KPK | 1,530 | Under construction. To be completed by 2025.[9][10] |
4 | Mohmand | Mohmand Tribal District, KP | 800 | Under construction. To be completed by December 2025.[11] |
5 | Diamer Basha | Near Chilas, KP & GB | 4,500 | Under construction. To be completed by February 2029.[12] |
6 | Kurram Tangi | North Waziristan, KP | 83 | Under construction. 61% completed.[13] |
7 | Mangla Refurbishment Project | Mirpur, Azad Kashmir | 310 | WAPDA successfully commissioned two refurbished generating units of the Mangla Hydel Power Station on May 23, 2022, increasing their capacity from 200MW to 270MW. Refurbishment of remaining units is under construction. Upon completion, it will enhance generation capacity of existing power stations from 1000MW to 1310MW.[14] |
Wind
[edit]In service
[edit]References: [1]
S/N | Station | Location | Capacity (MW) | In-service date |
---|---|---|---|---|
1 | Zorlu Enerji Pakistan (Pvt.) Ltd | Thatta, Sindh | 56 | 2013 |
2 | FFC Energy | Thatta, Sindh | 50 | 2013 |
3 | Three Gorges First Wind Farm | Thatta, Sindh | 50 | 2014 |
4 | Foundation Wind Energy – I | Thatta, Sindh | 50 | 2015 |
5 | Foundation Wind Energy – II | Thatta, Sindh | 50 | 2015 |
6 | Sapphire Wind | Thatta, Sindh | 53 | 2015 |
7 | Yunus Energy | Thatta, Sindh | 50 | 2016 |
8 | Metro Power Company | Thatta, Sindh | 50 | 2016 |
9 | Gul Ahmad Wind | Thatta, Sindh | 50 | 2016 |
10 | Master Wind Energy | Thatta, Sindh | 50 | 2016 |
11 | Tenaga Generai | Thatta, Sindh | 50 | 2016 |
12 | HydroChina Dawood Wind Power | Thatta, Sindh | 50 | 2017 |
13 | Sachal Energy Development | Thatta, Sindh | 50 | 2017 |
14 | United Energy Pakistan Wind Power | Thatta, Sindh | 99 | 2017 |
15 | Artistic Wind Power | Thatta, Sindh | 50 | 2018 |
16 | Act Wind (Tapal Wind) | Thatta, Sindh | 30 | 2018 |
17 | Hawa Energy | Thatta, Sindh | 50 | 2018 |
18 | Jhampir Power | Thatta, Sindh | 50 | 2018 |
19 | Three Gorges Second Wind Farm | Thatta, Sindh | 50 | 2018 |
20 | Three Gorges Third Wind Farm | Thatta, Sindh | 50 | 2018 |
21 | Tricon Boston Consulting-A | Thatta, Sindh | 50 | 2019 |
22 | Tricon Boston Consulting-B | Thatta, Sindh | 50 | 2019 |
23 | Tricon Boston Consulting-C | Thatta, Sindh | 50 | 2019 |
24 | Zephyr Power | Thatta, Sindh | 50 | 2019 |
25 | Din Energy Limited | Thatta, Sindh | 50 | 2022 |
26 | Lucky Renewables PVt. Ltd (TRICOM) | Thatta, Sindh | 50 | 2022 |
27 | Master Green Energy Ltd | Thatta, Sindh | 50 | 2022 |
28 | Act 2 Din Wind Pvt Ltd | Thatta, Sindh | 50 | 2022 |
29 | Artistic Wind Power Pvt. Ltd | Thatta, Sindh | 50 | 2022 |
30 | Indus Wind Energy Limited | Thatta, Sindh | 50 | 2022 |
31 | Lakeside Energy | Thatta, Sindh | 50 | 2022 |
32 | Liberty Wind Power-1 | Thatta, Sindh | 50 | 2022 |
33 | Gul Ahmed Electric Limited | Thatta, Sindh | 50 | 2022 |
34 | Liberty Wind Power-II (Pvt.) Ltd | Thatta, Sindh | 50 | 2022 |
35 | NASDA Green Energy (Pvt) Limited | Thatta, Sindh | 50 | 2022 |
36 | Metro 2 Wind Power Limited | Thatta, Sindh | 50 | 2022 |
Solar
[edit]In service
[edit]References: [1]
S/N | Station | Location | Capacity (MW) | In-service date |
---|---|---|---|---|
1 | Quaid-e-Azam Solar Park | Bahawalpur, Punjab | 100 | 2015 |
2 | Appolo Solar Development | Bahawalpur, Punjab | 100 | 2016 |
3 | Best Green Energy | Bahawalpur, Punjab | 100 | 2016 |
4 | Crest Energy | Bahawalpur, Punjab | 100 | 2016 |
5 | AJ Power Pvt. Ltd. | Khushab, Punjab | 12 | 2017 |
6 | Harappa Solar Pvt. Ltd | Sahiwal, Punjab | 18 | 2017 |
7 | Oursun Pakistan | Thatta, Sindh | 50 | 2019 |
8 | Gharo Solar | Thatta, Sindh | 50 | 2020 |
9 | Atlas Solar (Zhenfa Pakistan New Energy Company Limited) | Layyah, Punjab | 100 | 2022 |
10 | Meridian Energy (Pvt.) Ltd | Sukkur, Sindh | 50 | 2024 |
11 | HNDS Energy (Pvt.) Limited | Sukkur, Sindh | 50 | 2024 |
12 | Helios Power (Pvt.) Limited | Sukkur, Sindh | 50 | 2024 |
Bagasse / biomass
[edit]In service
[edit]References: [1]
S/N | Station | Location | Capacity (MW) | In-service date |
---|---|---|---|---|
1 | Jamal Din Wali-II | Rahim Yar Khan, Punjab | 26 | 12 Jun, 2014 |
2 | Jamal Din Wali-III | Rahim Yar Khan, Punjab | 27 | 3 Oct, 2014 |
3 | RYK Mills | Rahim Yar Khan, Punjab | 40 | 24 Mar, 2015 |
4 | Chiniot Power | Chiniot, Punjab | 63 | 28 Nov, 2015 |
5 | Hamza Sugar Mills | Rahim Yar Khan, Punjab | 15 | Mar, 2017 |
6 | The Thal Industries Corporation | Layyah, Punjab | 20 | |
7 | Almoiz Industries | Mianwali, Punjab | 36 | Feb, 2019 |
8 | Chanar Energy | Faisalabad, Punjab | 22 | Feb, 2019 |
Net metering
[edit]In service
[edit]References: [1]
As of 30 June, 2024, Pakistan has an installed net metering capacity of 2,498 MW.
S/N | Station | Capacity (MW) |
---|---|---|
1 | Net metering capacity of consumers in DISCOS | 2,165 |
2 | Net metering capacity of consumers in KE | 333 |
See also
[edit]- Electricity in Pakistan
- Energy policy of Pakistan
- List of hydroelectric power stations in Pakistan
- List of power stations in Asia
- List of largest power stations in the world
- Iran–Pakistan–India gas pipeline
References
[edit]- ^ a b c d e f g h "State of Industry Report 2024" (PDF). nepra.org.pk. Retrieved 22 January 2025.
- ^ a b "884MW Suki Kinari Hydropower Project". Retrieved 22 January 2025.
- ^ "Coal-fired Jamshoro power plant". www.brecorder.com. 15 July 2022. Retrieved 16 July 2022.
- ^ "Nuclear power generation". tribune.com.pk. 7 September 2020.
- ^ "PM breaks ground on 1200-megawatt Chashma-5 nuclear power plant". 14 July 2023.
- ^ "Suki Kinari Hydropower Project passes Reliability Run Test successfully". 14 September 2024. Retrieved 22 January 2025.
- ^ "WAPDA expedites construction work". dailytimes.com.pk. 14 April 2022. Retrieved 13 July 2022.
- ^ "Dasu Hydropower Project". www.wapda.gov.pk. Retrieved 13 July 2022.
- ^ "Tarbela 5th Extension". www.wapda.gov.pk. Retrieved 13 July 2022.
- ^ "Tarbela 5th extension project to generate electricity by 2025". 20 May 2023. Retrieved 30 May 2023.
- ^ "Mohmand Dam Project". www.wapda.gov.pk. Retrieved 13 July 2022.
- ^ "Diamer Basha Dam". www.wapda.gov.pk. Retrieved 13 July 2022.
- ^ "Kurram Tangi Dam". www.wapda.gov.pk. Retrieved 13 July 2022.
- ^ "Mangla Refurbishment Project". nation.com.pk. 24 May 2022. Retrieved 19 July 2022.