Kenié Hydroelectric Power Station

Coordinates: 12°38′31″N 07°47′09″W / 12.64194°N 7.78583°W / 12.64194; -7.78583
From Wikipedia, the free encyclopedia

Kenié Hydroelectric Power Station
Kenié Hydroelectric Power Station is located in Mali
Kenié Hydroelectric Power Station
Map of Mali showing the location of Kenié HPP.
Kenié Hydroelectric Power Station is located in Africa
Kenié Hydroelectric Power Station
Kenié Hydroelectric Power Station (Africa)
Kenié Hydroelectric Power Station is located in Earth
Kenié Hydroelectric Power Station
Kenié Hydroelectric Power Station (Earth)
CountryMali
LocationBaguinéda, Kati Cercle, Koulikoro Region
Coordinates12°38′31″N 07°47′09″W / 12.64194°N 7.78583°W / 12.64194; -7.78583
PurposePower
StatusProposed
Construction cost€110 million
Owner(s)Eranove
Operator(s)Kenié Énergie Renouvelable
Dam and spillways
ImpoundsNiger River
Installed capacity42 megawatts (56,000 hp)
Annual generation175 GWh

Kenié Hydroelectric Power Station is a 42 megawatts (56,000 hp) hydroelectric power station under development in Mali. The power station is owned by Eranove, a French company that specializes in the supply, distribution and management of electricity and water in Africa. In June 2015, working through its subsidiary, Kenié Énergie Renouvelable (Kénié Renewable Energy), Eranove signed a 30-year concession with the Malian government, to design, finance, build, operate and maintain this power station. Kénié Renewable Energy (KRE) is co-owned by the International Finance Corporation (IFC), a component of the World Bank Group. The energy off-taker for this power station is expected to be Société Energie du Mali (EDM-SA), the Malian public utility parastatal company.[1]

Location

[edit]

The power station would be located at Baguinéda, along the Niger River, in Kati Cercle, in the Koulikoro Region of southwestern Mali.[2] This is approximately 35 kilometres (22 mi), east of Bamako, the capital and largest city of Mali.[2][3]

Overview

[edit]

The design calls for generation capacity of 42 megawatts, equivalent to 175 GWh in annual production, capable of supplying 175,000 Malian homes.[2][4] The 30-year concession for this power station was awarded to Eranove on a build–own–operate–transfer (BOOT) arrangement. The Malian Council of Ministers approved the award in a cabinet meeting on 15 November 2018.[2]

Ownership

[edit]

Kenié Energies Revouvelables is the name of the special purpose vehicle company (SPV) that was awarded the concession contract, on behalf of Eranove, its parent company. The table below illustrates the ownership and shareholding in the SPV.[1][4]

Shareholding In Kenié Energies Revouvelables In 2018
Rank Shareholder Domicile Percentage Notes
1 Eranove France 80.0 [1][4]
2 International Finance Corporation United States 20.0 [1][4]
Total 100.0

Construction costs

[edit]

The construction costs were reported as €110 (US$124 million), in 2015 money.[1][4]

Other considerations

[edit]

In 2015 the expectation was to reach financial close in 2016, start construction after that and commission the power station in 2020, after four years of construction.[1][4] Although those plans did not materialize, as of April 2022, Eranove still hopes to develop this renewable energy infrastructure project in the future.[5]

See also

[edit]

References

[edit]
  1. ^ a b c d e f International Finance Corporation (18 June 2015). "IFC and Eranove Promote Renewable Energy Development in Mali with Kenié Hydropower Project". International Finance Corporation. Washington, DC, United States. Retrieved 8 April 2022.
  2. ^ a b c d Boris Ngounou (22 November 2018). "Mali: Kénié Renewable Energy can finally change capital's composition". Afrik21.africa. Paris, France. Retrieved 8 May 2022.
  3. ^ "Road Distance Between Bamako, Mali And Baguinéda, Mali With Map" (Map). Google Maps. Retrieved 8 May 2022.
  4. ^ a b c d e f Bonface (26 June 2018). "Eranove Group set to construct 42MW Kenié hydroelectric dam project in Mali". Construction Review Online. Nairobi, Kenya. Retrieved 7 May 2022.
  5. ^ Africa Intelligence (15 April 2022). "French firm Eranove still hopeful for Kenié power plant project". AfricaIntellignce.com. Paris, France. Retrieved 8 May 2022.