Friant Dam
Friant Dam | |
---|---|
Country | United States |
Location | Madera/Fresno Counties, California |
Coordinates | 37°00′02″N 119°42′19″W / 37.00056°N 119.70528°W |
Construction began | 1937 |
Opening date | 1942 |
Owner(s) | Central Valley Project United States Bureau of Reclamation |
Dam and spillways | |
Type of dam | Concrete gravity |
Impounds | San Joaquin River |
Height | 319 ft (97 m)[1] |
Length | 3,488 ft (1,063 m)[1] |
Width (base) | 267 ft (81 m)[1] |
Spillway type | Gated overflow, 1 center flotation drum gate, 2 obermeyer pneumatically actuated gates. |
Spillway capacity | 83,000 cu ft/s (2,400 m3/s)[2] |
Reservoir | |
Creates | Millerton Lake |
Total capacity | 520,528 acre⋅ft (642,062 dam3)[2] |
Inactive capacity | 120,000 acre⋅ft (150,000 dam3)[3] |
Catchment area | 1,638 sq mi (4,240 km2)[4] |
Surface area | 4,900 acres (2,000 ha)[2] |
Power Station | |
Turbines | 1x 15 MW, 1x 8 MW, 1x 2 MW[4] |
Installed capacity | 25 MW[4] |
Annual generation | 81,409,000 KWh |
Friant Dam is a concrete gravity dam on the San Joaquin River in central California in the United States, on the boundary of Fresno and Madera Counties. It was built between 1937 and 1942 as part of a U.S. Bureau of Reclamation (USBR) water project to provide irrigation water to the southern San Joaquin Valley. The dam impounds Millerton Lake, a 4,900-acre (2,000 ha) reservoir about 15 miles (24 km) north of Fresno.
Background
[edit]The valley in which Friant Dam and Millerton Lake now lie was once the location of the historic town of Millerton. Millerton was the first county seat of Fresno County.[5][6] In 1880, the first dam on the San Joaquin River was constructed by the Upper San Joaquin Irrigation Company roughly on the present site of Friant Dam. Built of local rock, the dam was an 800-foot (240 m) long, 6-foot (1.8 m) tall structure designed to divert water for the irrigation of 250,000 acres (100,000 ha). The project was abandoned in the wake of floods that destroyed the dam two years later.[7]
Friant Dam was originally proposed in the 1930s as a main feature of the Central Valley Project (CVP), a federal water project that would involve building an expansive system of dams and canals on the rivers of the Central Valley to provide water for agriculture, with secondary purposes of flood control, municipal supply, and hydroelectric power generation.[8] The CVP was authorized by the 1935 Rivers and Harbors Act, while $20 million of initial funding for Friant Dam was provided by the Emergency Relief Appropriation Act of 1935.[9]
Initial surveys of the Friant Dam site were carried out in November 1935 and continued through early 1936. In January 1938, a worker's camp was established near the town of Friant to house the laborers that would ultimately work on the dam. In the middle of the Great Depression, the Friant Dam site saw a huge influx of job seekers, many of whom had to live further away in surrounding cities. More than 50,000 people attended the groundbreaking of the dam on November 5, 1939 in a celebration that is now known as "one of the greatest in San Joaquin Valley history".[10]
Construction
[edit]Construction of Friant Dam began with blasting and excavation of the dam site to remove more than 1,200,000 cubic yards (920,000 m3) of loose material above the bedrock. Before any concrete was laid on the dam's main wall, the underlying rock was extensively grouted to fill in 725 holes and seams that might otherwise cause instability in the foundation. The concrete used in the dam's construction was made from sand and gravel excavated from the San Joaquin River floodplain about 3 miles (4.8 km) below the dam to form Lost Lake. Notably, more than 5,400 ounces (150 kg) of placer gold – worth $176,000 at the time – were uncovered in the excavation site.[11] A branch line of the Southern Pacific Railroad delivered this material to a concrete mixing plant, which could produce up to 6,000 cubic yards (4,600 m3) of concrete per hour, directly adjacent to the construction site.[12] In July 1940, the San Joaquin River was diverted through a wooden flume so that work on the foundations could begin.[11]
On July 29, the first concrete was poured into the main body of Friant Dam. In order to keep the structure in line, the dam was built in a series of blocks or forms, each measuring 50 feet (15 m) square. Concrete was placed via a massive steel trestle system 210 feet (64 m) high and 2,200 feet (670 m) long, along which ran small powered railcars that delivered buckets of concrete from the mixing plant. Two gantry cranes lifted the buckets from the cars and poured them onto the forms. In summer 1941, the labor force reached a peak of 1,500, and the monthly record for concrete placement, at 228,000 cubic yards (174,000 m3), was set in August.[13]
During the dam's construction several Native American burial sites had their graves removed and re-interred.
The workforce scrambled to complete the main wall of the dam after an act of the War Production Board (WPB) suspended resources in order to assist U.S. military efforts in World War II. The dam was topped out on June 16, 1942, just under two years after the first concrete was poured. However, the spillway gates, the water release valves and the two irrigation canals Friant was intended to support remained unfinished in the wake of the WPB's order.[11]
The war, however, did not completely halt construction. Less than a year later, the WPB "[determined] the completion of the Madera Canal and the installation of valves at the Friant Dam, necessary for war-time food and fiber production" – allowing construction to resume on a limited scale.[11] A pair of control valves were borrowed from Hoover Dam, allowing the closure of the river outlets and Millerton Lake began to fill on February 21, 1944. Work on the Madera Canal, the smaller of the two irrigation canals serviced by Friant Dam (the other, the Friant-Kern Canal, would not be completed for another four years), was completed in 1945 and water ran for its entire length for the first time on June 10, with irrigation deliveries commencing one month later.[11]
The dam was formally dedicated on July 9, 1949 by California governor Earl Warren, who declared that the water furnished by Friant Dam and its canals would help the San Joaquin Valley to "become a modern Eden" as water was released into the partially completed Friant-Kern Canal for the first time.[14] More than three thousand people, mostly residents of the San Joaquin Valley, attended the ceremonies.[15]
[The dam is] but a lifeline to preserve and enhance our American civilization. This is a line of creation, built to unlock the fertility of the rich soil, to resist drought, to overcome floods, to provide outdoor recreation, and to generate cheap power that will improve the living conditions of millions of our citizens."
– Secretary of the Interior Harold Ickes at Friant Dam dedication[15]
Operations and usage
[edit]Friant Dam's primary purpose is to capture the fluctuating flows of the San Joaquin River and divert the water for irrigation through the Friant-Kern and Madera Canals. The Friant-Kern Canal is 151.8 mi (244.3 km) long, extending south from the dam to the Kern River near Bakersfield, and has an initial diversion capacity of 5,000 cubic feet per second (140 m3/s); the 35.9-mile (57.8 km) Madera Canal, which has a capacity of up to 1,000 cubic feet per second (28 m3/s), travels north from the dam to the Chowchilla River. Together, these canals provide irrigation water to some 837,000 acres (339,000 ha) of the San Joaquin Valley. In 1990, farmers who received their water from Friant Dam produced more than $1.9 billion worth of 90 different kinds of crops.[2]
Millerton Lake has a capacity of 520,528 acre-feet (642,062 dam3) at normal maximum pool, with a surcharge (above spillway gates, but below the dam crest) capacity of approximately 91,000 acre-feet (112,000 dam3) for a total capacity of 611,500 acre-feet (754,300 dam3). About 170,000 acre-feet (210,000 dam3), or 32.7% of the reservoir's regular capacity, is reserved for flood control between October and January to protect against rain floods, while between February and July, this is increased to 390,500 acre-feet (481,700 dam3) – 75.0% – to provide space for snowmelt floods.[16] The dam is operated to maintain a flow of 6,500 cubic feet per second (180 m3/s) or less on the San Joaquin River at Mendota, 60 miles (97 km) downriver. However, large snowmelt floods often exceed the capacity of the dam and reservoir and force larger releases downstream, potentially causing damage to riverside property and infrastructure.[4]
The dam is also used to generate up to 25 megawatts (MW) of hydroelectric power. The penstock releasing water into the Friant-Kern Canal is fitted with a Kaplan turbine with a capacity of 15 MW, and the Madera Canal penstock is equipped with a smaller 8 MW turbine. The smallest hydroelectric generator, with a capacity of 2 MW, is located at the outlet works on the base of the dam and produces power from water releases that serve local farms along the San Joaquin River directly downstream from Friant Dam, as well as releases to a fish hatchery below the dam and for wildlife management purposes.[4]
Expansion
[edit]Because of its relatively small storage capacity relative to the average annual discharge of the San Joaquin River – 520,528 acre-feet (642,062 dam3) versus 1,790,000 acre-feet (2,210,000 dam3) – Friant Dam often has to release excessive amounts of water that could be otherwise used for irrigation or power generation, also causing downstream damage. From 1981 to 2011, an average of 450,000 acre-feet (560,000 dam3) was spilled each year because the reservoir was unable to contain it.[17] The USBR has proposed increasing the height of Friant Dam by up to 140 feet (43 m), nearly tripling the reservoir's storage capacity to 1,390,000 acre-feet (1,710,000 dam3). A smaller 60-foot (18 m) raise would increase storage capacity to 860,500 acre-feet (1,061,400 dam3), while a 25-foot (7.6 m) raise would increase storage capacity to 652,500 acre-feet (804,800 dam3). The increase in height would also allow for the generation of between 4.7–30.4 MW of additional power.[18][19]
Another proposal to increase storage in the upper San Joaquin River basin is Temperance Flat Dam, which would be located in the San Joaquin River canyon upstream of Friant Dam and impound between 460,000 to 2,775,000 acre-feet (567,000 to 3,423,000 dam3) of water.[20] The proposed dam would stand 415 to 840 feet (126 to 256 m) high above the river, and it would capture most of the floodwater that would otherwise be spilled from Friant Dam. However, Temperance Flat has come under heavy controversy because it would flood a large scenic section of the San Joaquin River gorge, negatively affect wildlife in the river and inundate two upstream hydroelectric power plants, causing a net loss in power generation.[21] The water supplied from such a dam would be very expensive, ranging from $1000–1500 per acre foot (area farmers currently pay about $60 per acre foot). Raising Friant Dam would likely produce similar increases in the cost of irrigation water.[22]
Environmental impacts
[edit]By diverting most of the San Joaquin River for irrigation, the Friant Dam has caused about 60 miles (97 km) of the river to run dry except in high water years when floodwaters are spilled from the dam. The desiccation of the river has caused the degradation of large stretches of riverside habitat and marshes, and has nearly eliminated the historic chinook salmon run that once numbered "possibly in the range of 200,000 to 500,000 spawners annually".[23] Reduction in flows has also increased the concentration of pesticide and fertilizer runoff in the river contributing to pollution that has further impacted aquatic species.[24]
On September 13, 2006, after eighteen years of litigation, environmental groups, fisherman and the USBR reached an agreement on releasing part of the water currently diverted into the irrigation canals into the San Joaquin River in order to help restore the river and its native fish and wildlife. The first water was released on October 2, 2009 at a rate of 185 cubic feet per second (5.2 m3/s).[25] By 2014, these "restoration flows" will be increased to 302,000 acre-feet (373,000 dam3) per year, or 417 cubic feet per second (11.8 m3/s), on top of the 117,000 acre-feet (144,000 dam3) that is currently released for agricultural purposes. However, the river restoration project will cause a 12–20% reduction in irrigation water delivered from Friant Dam.[26]
See also
[edit]- Water in California
- California Water Wars
- List of dams and reservoirs in California
- List of largest reservoirs of California
- List of the tallest dams in the United States
References
[edit]- ^ a b c "Friant Dam – Dimensions". Friant Division Project. U.S. Bureau of Reclamation. 2009-06-04. Retrieved 2012-04-04.
- ^ a b c d "Friant Division Project". Central Valley Project. U.S. Bureau of Reclamation. 2011-04-21. Archived from the original on 2011-11-12. Retrieved 2012-04-04.
- ^ Ritzema, Randall S.; Newlin, Brad D.; Van Lienden, Brian J. (October 2001). "Appendix H: Infrastructure" (PDF). CALVIN Project. University of California Davis. Archived from the original (PDF) on 2017-11-06. Retrieved 2014-01-25.
- ^ a b c d e "Draft Background Report on Friant Dam Operations" (PDF). San Joaquin River Restoration Program. 2008-02-07. Archived from the original (PDF) on 2011-10-18. Retrieved 2012-04-04.
- ^ "Historic Posts, Camps, Stations and Airfields – Fort Miller". California State Military Museum. Retrieved 2012-04-05.
- ^ McKinney, John. "Millerton Lake State Recreation Area". California Department of Parks and Recreation. Retrieved 2012-04-05.
- ^ "Historic Conditions in the San Joaquin River Watershed". Sierra Foothill Conservancy. 2006-02-15. Archived from the original on 2013-04-16. Retrieved 2012-04-05.
- ^ "Central Valley Project". U.S. Bureau of Reclamation. 2011-04-21. Retrieved 2012-04-05.[permanent dead link ]
- ^ Krovoza, Joe (January 1992). "Congressional Legislation to Benefit Fish and Wildlife in California's Central Valley" (PDF). Environs. University of California Davis. Retrieved 2012-04-05.[permanent dead link ]
- ^ "Governor Makes Plea For Public Ownership At Friant Dam Celebration". The Rural Observer. 2 (6). Online Archive of California. 1939.
- ^ a b c d e Autobee, Robert (1994). "Friant Division: Central Valley Project" (PDF). Bureau of Reclamation History Program. U.S. Bureau of Reclamation. Archived from the original (PDF) on 2016-05-15. Retrieved 2012-04-04.
- ^ Billington, Jackson & Melosi 2005, pp. 343–344.
- ^ Billington, Jackson & Melosi 2005, p. 344.
- ^ "Water For A New Eden: The Friant-Kern Canal answers prayers of farmers who work some of California's richest but thirstiest land". Life. Vol. 27, no. 4. 1949-07-25. p. 25.
- ^ a b Brewer 2001, p. 40.
- ^ "Friant Dam Flood Control Requirements" (PDF). U.S. Army Corps of Engineers. San Joaquin River Restoration Program. 2009-12-15. Archived from the original (PDF) on 2011-10-18. Retrieved 2012-04-05.
- ^ "Friant Dam Flood Releases Continue – More Water Storage Needed". California Ag Network. Associated Press. 2011-01-25.
- ^ "Friant Dam Enlargement" (PDF). Upper San Joaquin River Basin Storage Investigation. U.S. Bureau of Reclamation. October 2003. Retrieved 2012-04-05.
- ^ "Attachment C2: Cost Estimate Worksheets" (PDF). Raise Friant Dam (Chapter 2). U.S. Bureau of Reclamation. Retrieved 2012-04-05.
- ^ "Temperance Flat Reservoir: Surface Storage Option Technical Appendix to the Phase 1 Investigation Report" (PDF). Upper San Joaquin River Basin Storage Investigation. U.S. Bureau of Reclamation. October 2003. Archived from the original (PDF) on 2016-03-03. Retrieved 2012-04-05.
- ^ "California Rivers: San Joaquin River". Friends of the River. Archived from the original on 2015-09-24. Retrieved 2012-04-05.
- ^ Nelson, Barry (2010-03-10). "Dam Advocates Make Case for the Virtual River". Natural Resources Defense Council. Retrieved 2012-04-05.
- ^ Yoshiyama; et al. (2001). "Historical and present distribution of chinook salmon in the Central Valley drainage of California". Contributions to the Biology of Central Valley Salmonids, Fish Bulletin. 179: 309–362.
- ^ "Restoring the San Joaquin River: Following an 18-year legal battle, a great California river once given up for dead is on the verge of a comeback". Natural Resources Defense Council. Retrieved 2012-04-05.
- ^ Sheehan, Tim (2009-10-02). "Friant Dam releases water to begin river rebirth". The Fresno Bee.
- ^ "Restoration Flows" (PDF). Friant Water Authority. Archived from the original (PDF) on 2012-04-07. Retrieved 2012-04-05.
Works cited
[edit]- Billington, David P.; Jackson, Donald C.; Melosi, Martin V. (2005). The History of Large Federal Dams: Planning, Design, and Construction. Government Printing Office. ISBN 0-16072-823-1.
- Brewer, Chris (2001). Historic Kern County: An Illustrated History of Bakersfield and Kern County. San Antonio, TX: HPN Books. ISBN 1893619141.
External links
[edit]- Friant Water Authority
- Live hydrologic data for Friant Dam Archived 2012-01-29 at the Wayback Machine
- Buildings and structures in Fresno County, California
- Buildings and structures in Madera County, California
- Dams in California
- Hydroelectric power plants in California
- San Joaquin Valley
- United States Bureau of Reclamation dams
- Dams completed in 1942
- Energy infrastructure completed in 1942
- Dams on the San Joaquin River
- Central Valley Project
- 1942 establishments in California