Jump to content

Construction of Berlin Brandenburg Airport

From Wikipedia, the free encyclopedia

Berlin Brandenburg Airport was originally planned to open in October 2011, five years after starting construction in 2006. However, the project encountered a series of successive delays due to poor construction planning, execution, management, and corruption. The Airport finally received its operational licence in May 2020,[1] and opened for commercial traffic on 31 October 2020, 14 years after construction started and 29 years after official planning was begun.[2] Schönefeld's refurbished passenger facilities were incorporated as Terminal 5 on 25 October 2020[3][4][5] while all other airlines completed the transition from Tegel to Berlin Brandenburg Airport by 8 November 2020.[6]

Overview

[edit]

The construction of Berlin Brandenburg Airport suffered from continued delays which were caused by an array of issues.

The most significant cause for the continuing delays was the fire protection and alarm system. In the terminal building, the system was not built according to the construction permit and failed the mandatory acceptance test necessary to open the airport. FBB proposed an interim solution employing up to 700 human fire spotters, which the building supervision department of the local Dahme-Spreewald district rejected.[7] Inspectors uncovered flaws in the wiring, programming and implementation of the highly complex system designed by Siemens and Bosch. The system automatically controls sprinklers, smoke extractors and fire doors.[8] For aesthetic reasons, designers decided that the terminal would have smoke extraction ducts in its ceiling but that they would not exhaust to its rooftop. During a fire, smoke would be pumped from the ceiling into a shaft running down and through the basement below the structure.[9] This required the natural rising behaviour of hot air in the shaft to be reversed. Achieving this on the scale necessary for this airport is a unique undertaking and so far this elaborate smoke extraction system has not worked as planned.[10] To meet the acceptance test requirements, large scale reconstruction work of the fire system might be needed.[11] It emerged that Alfredo di Mauro, who designed the fire safety system, was not a qualified engineer. While his business cards stated he was an engineer, he was actually qualified as an engineering draughtsman.[12] Di Mauro was dismissed by the airport company in early May 2014. In the termination notice, the company cited "serious defects" in his work and that trust in their relationship was "now finally shattered". The airport company went on to state that Di Mauro's plans would be "disposed of". The system was to be rebuilt and divided into three areas in order to make it "manageable". The cost of this work was reported as being a nine-digit figure.[13]

Another major factor impacting on the construction of the airport was insolvency of general planner Planungsgemeinschaft Flughafen Berlin Brandenburg International (pg bbi) and the dismissal of the Gerkan, Marg and Partners architects. Inspectors have uncovered many examples of poor workmanship due to a lack of proper supervision and documentation, most notably concerning the wiring. Reports have surfaced about cable conduits that hold too many cables or hold cables in incompatible combinations, such as phone lines next to high voltage wires. A total of 60 kilometres (37 mi) of cooling pipes were allegedly installed with no thermal insulation. To correct this, the demolition of numerous walls may be necessary. Furthermore, exterior vents appear to be in improper locations, allowing rainwater from the western facade to enter them.[11]

Timeline

[edit]
Construction delays[14]
Announcement Opening date
5 September 2006 (original) 30 October 2011
25 June 2010 3 June 2012
7 May 2012 17 March 2013
27 October 2012 27 October 2013
January 2013 on/after 2014
8 January 2014 on/after 2015
24 February 2014 on/after 2016
14 May 2014 on/after 2017
December 2014 2nd half of 2017
21 January 2017 2018
15 December 2017 31 October 2020

2006

[edit]

After nearly 15 years of planning, actual construction work for Berlin Brandenburg Airport began on 5 September 2006.[15] When construction began, FBB announced 30 October 2011 as the opening day for the new facility.[16] To make way for the new airport, two villages were removed. The 335 inhabitants of Diepensee received compensation and were offered new homes in Königs Wusterhausen, a move that was completed by late 2004. The 35 villagers of Selchow were resettled to Großziethen in mid-2005.[17][18]: 16 

2007

[edit]

In November 2007, the BER-Infotower opened a 32-metre-high (105 ft) public observation tower and information center.[19] It was part of the airport's visitor facilities, which also had a webcam of the construction progress.[20] The transparent and twisted structure was originally intended to be temporary, with a scheduled removal announced in 2016.[21]

2008

[edit]

Construction of the terminal building began in July 2008.[22]

Tempelhof Airport was officially closed on 30 October 2008.

2010

[edit]
Construction progress at today's Terminal 1 as of 2010

On 8 and 9 May 2010, the airport celebrated its topping out with open days at the airport site.[23] A few days after 14 June 2010 topping out ceremony, FBB announced that construction deadlines could not be met. [24]

2011

[edit]

On 30 October 2011, the railway line and terminal station were ready for service, however no scheduled trains would operate until the opening.

Operating tests and service trials began on 24 November 2011, based on the anticipated opening date of 3 June 2012. A total of 12,000 volunteers participated in simulated check-in, security screening, boarding and baggage claim. The tests used 15,000 pieces of luggage in the automated baggage processing system, covered night-time operations and emergency scenarios.[25] This phase also saw the acceptance tests of various airport systems. It became clear on 8 May 2012 that the building could not open on schedule, officially due to the failure of the fire protection system. In reality, according to a Brandenburg State Audit report in February 2016 the usability of the airport was at 56.2%; for example, there were no ticket counters and the escalators did not work. The report went on to say there was no realistic chance that it could be used "reasonably successfully" in 2012.[26] Legal implications concerning the failed 2012 opening were expected after the release of the 2016 report.[27]

2012

[edit]

As the new date drew nearer, airlines amended their timetables to reflect their plans to operate from BER. On the retail side of the airport, shops and restaurants prepared for the opening. As the airports in Tegel and Schönefeld were to close once the last flights of 2 June had been serviced, a major logistics operation for moving the airports' infrastructure was launched. Vehicles, equipment and supplies that were needed at Tegel until the final moments would have been transported to BER during the night of 2–3 June. To allow this, the authorities planned to restrict the highways linking the two airports (A113, A100 and parts of A111) to airport traffic only.[28] Rundfunk Berlin Brandenburg, the national broadcaster for Berlin and Brandenburg, scheduled 24 hours of continuous live coverage of the airport move.[29] A special Lufthansa flight to Frankfurt Airport, operated with an Airbus A380, was scheduled as the first departure from the new airport on 3 June at 06:00.[29]

On 8 May 2012 just 26 days before the move, FBB again postponed the opening date. The postponement led to the cancelling of moving plans and in some cases reversing actions already completed. It cited technical difficulties, primarily concerning the fire safety and smoke exhaust systems for the delay.[30] As a result, FBB dismissed the director for technical affairs Manfred Körtgen and replaced him with Horst Amann. It also announced 17 March 2013 as the new opening date for BER. However, this was soon met by doubts due to the large number of construction flaws and problems that inspectors continued to find.[31]

In early September 2012, FBB further postponed the opening to 27 October 2013.[32] Again, media and experts (most notably Peter Ramsauer, Federal Minister for Construction and Infrastructure) voiced doubts about the deadline.[33]

2013

[edit]

FBB announced on 6 January 2013 that the opening would be further delayed, at least until 2014; however, no definite opening date was given.[10] Klaus Wowereit resigned as chairman of the supervisory board and was replaced by Matthias Platzeck, who previously had served as his deputy. The board also dismissed Rainer Schwarz, the CEO of FBB, on 16 January.[34] By January 2013, FBB had announced and cancelled four official opening dates.[8][10] FBB named Hartmut Mehdorn, previously CEO of Deutsche Bahn (1999–2011) and Air Berlin (2011–2013) as Schwarz's replacement on 8 March 2013.[35]

Due to the rising passenger numbers at Berlin airports and delays to BER, concerns were voiced in 2013 that the new airport might be too small as passenger numbers at existing Berlin airports were approaching the BER design capacity.[8]

2014

[edit]

On 8 January 2014, FBB announced the airport would not open that year.[36] Mehdorn stated on 24 February 2014 that it was unlikely the airport would open before 2016.[37] In remarks made in August 2014, he pointed towards 2017 or 2018.[38] Mehdorn announced no opening date by 14 October 2014, so a special commission established by the Brandenburg Parliament retained oversight of the project.[39][40][41][42][43]

The initial design for the main hall, known as "the monster" to construction workers, called for a single exhaust system. Revised plans called for multiple systems controlled by 90 km (56 mi) of wiring. By 19 May 2014 Siemens had not yet designed the wire harnesses.[44] These problems are forcing the initial construction budget to skyrocket.[10]

BBI sought to open the north pier for use by three to ten flights per day as a test, though other parts of the airport would not be operational for some time. It requested that Technischer Überwachungsverein (Technical Inspection Association, TÜV) review the facility for safety and compliance to Brandenburg building codes. In its assessment report issued on 29 July 2014, TÜV found that some lightning rods were missing and that the back-up generator powering the sprinkler system did not provide adequate power. One source with the TÜV stated, "What the airport ordered was sufficient for a circus tent, but [if power fails] not for the dimensions of the terminal."[45] The 18-kilometre-long (11 mi) exhaust system to remove smoke from a fire was also reported to be leaking.[46]

Citing dissatisfaction with construction progress, members of the airport board indicated during their 8 December 2014 meeting that they were beginning the search for a new CEO, although Mehdorn's contract ran through 2016.[47] One week later, Mehdorn announced he would resign as soon as the board named a successor, but no later than June 2015.[48][49] Karsten Mühlenfeld, former head of Rolls-Royce Germany,[50][51] replaced him as airport CEO in March.

2015

[edit]

The search for a general planner was eventually stopped in February 2015.[52]

On 20 March 2015, Mehdorn again faced questions from the Investigative Commission of Berlin's parliament.[53][54] Mehdorn eventually ceased all public duties on 21 May 2015, citing health concerns.[55] Berlin's mayor Michael Müller was appointed the new head of the supervisory board (Aufsichtsrat) on 3 July 2015.[56] However, he had disagreements with Mühlenfeld, primarily over the opening date.[57][58][59][60] Led by Mayor Müller, the board insisted on an opening in 2017.[61]

A former manager for BER was taken into remand for alleged bribery on 13 May 2015;[62] an Imtech manager was alleged to have given him bribes at a highway gas station in 2012.[63] Imtech built parts of the fire exhaustion system.

The German branch of (Dutch) Royal Imtech filed for bankruptcy on 6 August 2015,[64] and its parent company went bankrupt a few days later.[65][66][67] As a result, Martin Delius, leader of the commission of inquiry into the failures during the airport's construction, stated that the planned opening in late 2017 was doubtful.[68]

Also in August 2015, new allegations of corruption were published in the Bild newspaper.[69] According to the paper, some large contractors filed additional payment demands after completion of their respective projects within BER, and received the complete requested payments with almost no objections. Lawyers reviewing the process stated that the high percentage of claims granted approval was unique and extraordinary. As a result, all payments beginning from the start of the project were to be reviewed.[69] The projected opening in 2017 was declared unlikely around the same time.[70] At the end of August 2015, though, the new airport head presented the Schüßler plan as the course of action.[71] When Mehdorn testified before the Investigations Commission of the Berlin parliament in March 2015, he stated that redesigns to correct the exhaust system would not be completed until "after the summer break," and that the terminal will not be finished until March or April 2016.[53]

An immediate halt to all construction efforts in the terminal was ordered on 21 September 2015 because a collapse of the main roof was imminent. This was done according to Dahme-Spreewald district's construction supervision.[72] The shutdown lasted two weeks.[73][74][75][76] Furthermore, 600 fire protection walls had to be replaced because they were built out of aerated concrete blocks that provided insufficient fire protection. The mortar was found to be inadequate as well.[77][78]

2016

[edit]

By 2016, further consequences of the low likelihood of a 2017 opening appeared on the horizon. Tegel's permit was set to expire at the end of 2017; but if Tegel was closed before BER was opened, massive disruptions would occur due to Tegel handling over 60% of all passenger traffic in Berlin.[79] This led to expectations that pressure to open BER would mount drastically.[80]

As of 7 February 2016, 24 opaque skylights (which can allow smoke to escape) in the main gangway required approval. The opaque skylights are part of the fire exhaustion system.[81] FBB spokesman Daniel Abbou confirmed to Berliner Morgenpost that the 24 skylights may need "individual approval" rather than a blanket approval for all.[27][82]

As of April 2016, the fire exhaustion system experienced further lapses that would delay a new issuing of the rework permission for the fire suppression system. The underground railway station also needed a redesign for the underground part of the fire exhaustion system. Incoming or departing trains might suck smoke into the station, so air flow guidance was needed to avoid this effect. However, the airport could not decide upon the method by itself, as permission is needed from the Federal Railway Authority (Eisenbahnbundesamt). The construction authority of the district of Dahme-Spreewald, Eisenbahnbundesamt, and the airport thus needed to join in the redesign effort. The plans on how to rebuild the underground part would not be finished before June. Thus, with no plans, the district could not grant the redesign permission. As such, the airport could not start the redesign effort before the beginning of July (assuming that the district would promptly check on the plans). As such, the construction process was delayed by at least 8 months.[83] On 17 April 2016, it became clear that the district would conduct an intensive investigation into the construction plans. Airport head Mühlenfeld thus publicly demanded that the parties come to grips with their decision.[84]

Also in April 2016, press spokesman Daniel Abbou was fired after giving "too honest" an interview. He had stated that billions of euros had been squandered, and that only someone "dependent on medication will give you any firm guarantees for this airport."[85][86] On 25 April 2016, Mühlenfeld stated that "surprisingly, demands (towards a simulation of the problem) are higher than expected." In fact, the Federal Railway Authority demanded that the commuter trains be simulated at speeds up to 100 kilometres per hour (62 mph) when entering or leaving the station. This means it would take more time to simulate the exact solution for the underground railway station.[87] The Federal Railway Authority also called for the simulation of emergency/evacuation scenarios.[88][89] To prevent suffocation in an emergency, glass towers are to be built inside the railway station that connect to openings in the roof, which will provide fresh air.[90][91] Mold seems to be persistent, the railway station is already ventilated from time to time by mobile fans.[92]

By May 2016, it had become clear that an expedited approval of the underground station would not happen.[93] Because of this, the timetable for opening had to be pushed back to at least 2018.[94] Specifically, the airport was unable to conform to the fifth appendix for the construction permission, therefore it was declined. The airport found it disappointing that there was no quick approval of the underground redesign efforts as of 10 June. Instead, the authority stated that a filing for the fifth appendix was incomplete and insufficient. The vice district administrator for Dahme-Spreewald, Chris Halecker, decried political pressure from the airport.[95]

On 23 August 2016, a former FBB department head admitted in court to taking €150,000 in bribes from Imtech, on a parking lot next to a highway in 2012.[96] At the end of August 2016 it was announced that the airport had missed an internal deadline, and that the permissions for the next phase of construction could not be issued. This was because the fire protection system for the connection between the airport and railway station lacked sufficient documentation.[97] These conditions were met on 6 October 2016.[98] The conditions for the final construction approval would only be met on 27 January 2017.[99][100]

The project management missed a 7 October 2016 deadline to announce a definite opening date for the airport.[101] In October 2016, traffic commission chairman Burkert declared that an opening in 2017 was impossible.[102] An 11 October 2016 committee session found that motors used to open and close windows would not operate above 30 °C (86 °F), necessitating their replacement.[103] Three thousand smoke detectors went missing, but were later found.[104][105] Technical issues involving the electric doors became public on 18 January 2017. It was discovered that 80% of the doors would not open, which created concerns around venting of smoke in a fire.[106] The sprinkler system had sustained failures in the south pier.[107] The sprinkler heads were replaced for increased water flow, but the pipes were too thin to carry it; as a result the ceiling needed to be opened for the pipes to be replaced.[108] The new low-cost terminal T2 will possibly be delayed until after 2020.[109] It was revealed in a newspaper report that the airport could not open before 2018, and that this had been known by the airport for three years despite public statements otherwise.[110]

The main construction permit (that is, the permission of the authority of Berlin issues to construction firms) was destined to expire. This would mean all construction work would have to terminate on 23 November 2016. A new law, referred to as a "Lex BER", extended the construction permission for ongoing projects.[111]

By the end of 2016, unfinished construction and corrective work indicated clearly that an opening prior to late 2017 was unlikely.[112][113][114][115] In December 2016, Mühlenfeld hinted at a possible 2018 opening;[116][117][118][119] Ryanair marketing head Kenny Jacobs suggested March 2018.[120]

2017

[edit]

In January 2017, it became clear that the airport would not open in 2017,[121][122][123] with some estimates suggesting that the airport would open in 2018 or 2019, at the latest.[124][125][126] On 6 March 2017, Lütke-Daldrup was appointed to replace Mühlenfeld as the head of the construction project[127][128][129] and Rainer Bretschneider was appointed head of the supervisory board.[130] The target opening was pushed to 2018 or 2019,[131][132] with 2020 as a possible option.[133] In Aug 2017 the Berliner Zeitung reported that the airport's remaining funds would run out in 2018.[134]

As of May 2017, estimates suggested the airport could open in late 2018 or early 2019, but an opening in 2020 was not ruled out.[135] The opening date of 2019 had already been described as ambitious[136] and even the new opening date of 2020 was called into question. On 23 November 2017, exactly 2,000 days after the originally planned opening date in 2012, a TÜV report listed additional deficits. It is possible that the new deficits will cause an additional delay of up to two years, with an opening in 2021.[137] At the end of 2017, autumn 2020 was announced as the new official opening date.[138]

The recent bankruptcy of Air Berlin was another problem for the airport. With Air Berlin absent it became even clearer that the airport would not become a major hub.[139] The number of connections a person can catch would be immediately reduced and Tegel was too far away to be any help in this regard. Interested citizens forced a non-binding public quorum that was held parallel to the federal election, asking whether Tegel should remain open if BER was already in operation. The majority of Berlin's citizens agreed.[140]

In November 2017, an audit of the entire airport by Germany's technical supervision service TÜV uncovered more significant lapses in the fire and emergency systems, further pushing back estimates.[141]

2018

[edit]

In January 2018, it was disclosed that the airport head is simultaneously earning a monthly wage and a retirement pension as a former state secretary of the state of Berlin, a situation described as a "scandal" and potentially illegal.[142] The airport was scheduled to open in 2020 with a total cost exceeding €7 billion.[143][144] The airport chief executive gave his assurance that the date would be met.[145]

In March, it was reported that 750 display screens have already reached the end of their service life and will need to be replaced, as they were switched on for 6 years despite the airport not being open.[146][147]

Planned extensions of the airport were also seen as a threat to opening in 2020, according to the airport's engineering advisor Faulenbach da Costa.[148] More people than previously expected would be moving through the main terminal, causing an increase in fire emergency load, with even more passengers arriving through the railway station in the basement. Thus smoke systems would need to be adjusted once again.[149] Lufthansa board member Thorsten Dirks [de] said "the airport will be torn down and rebuilt."[150][151]

Personnel changes continued to affect the project, with the head of the technical department Jörg Marks leaving the company on 19 April 2018, and Brandenburg's state secretary for airport affairs Rainer Bretschneider going into retirement in June.[152][153][154]

The airport failed a mandatory TÜV acceptance test in May 2018, with 863 issues found in the electric wiring.[155] Wiring remained a major issue in 2018. The all-around test was planned to commence sometime in September 2018 but it was postponed to June 2019 because the wiring was still flawed.[156] Also in May 2018, Siemens, the software supplier for the smoke suction system, testified before Berlin's senate's airport commission stating that the airport had not yet delivered essential paperwork required for them to complete the suction software.[157] In the same month the airport faced new legal issues as concerned citizens claimed that the aeroplane noise caused by the new airport would violate their rights to be heard. A few months later Germany's supreme court ruled that nighttime flights over BER are lawful.[158]

In June Berlin's assembly formed a new committee of inquiry to uncover responsibility for ongoing construction lapses and to investigate possible sources of further delay.[159] The still-unopened airport announced plans to expand with a second terminal in July, with construction to be done by Zechbau Bremen for a total cost of €200 million.[160][161]

2019

[edit]
Exterior of Terminal 2, which had been added in the last phases of construction to provide further capacity

It was reported at the start of January 2019 that the construction oversight authority was unwilling to permit the Terminal's wiring as is, because it was too tangled.[citation needed]

Berlin's Tagesspiegel reported that Bosch (fire detection) and Caverion (sprinklers) were unwilling to participate in a hearing of Berlin's parliament on 14 March 2019. It was then assumed that the airport would not open until 2020.[162] The fire protection malfunction seems to be too significant to keep 2020 as an opening date.[163]

On 28 March 2019, it was reported that a software update for the fire alarm system planned to be ready by 29 March would be delayed until late May. TÜV Rheinland warned that there were still considerable problems with the system, and stated that if there were any further delays the October 2020 opening date would be missed.[164] On 16 April 2019, the smoke suction system nicknamed "the Monster" finally received approval from TÜV,[165] afterwards by an expert representing the State.[166]

In May 2019, it was reported that sand-lime brick used in the foundations of the airport were not sufficiently rated for load, necessitating a costly replacement of much of the underground cabling and reinforced concrete beams. According to a subsequent investigation the problem had been known since 2012. The problematic plastic anchors that were earlier found to be unsuitable for fire were also found not suitable for sand-lime brick. As stated by Deutsches Institut für Bautechnik, it is not possible to approve already-installed anchors after the fact.[167] Later in May the head of the airport Lütke-Daldrup stated that "it cannot be guaranteed entirely anymore" that the airport will open in October 2020.[168] Unapproved screw anchors made of plastic not rated for fire seem to have been the reason for the new delay.[169][170][171]

Also known since 2012 were problems with the cable ducts: 700 kilometres (430 mi) of cable needed to be replaced due to water overflow within the cable ducts next to the southern runway. The ducts were not leakproof against incoming water, and had eroded in the decade since they were first installed. The repairs were scheduled to start later in 2019. According to airport head Lütke-Daldrup, the planned opening date of October 2020 was not affected by the cable duct problem, as the repairs could continue while the airport was in operation.[172] German minister of traffic Mr Scheuer however reiterated his concerns that the sand lime brick and cable duct issues could delay the opening beyond 2020.[173] Conservative party member Graeff stated that if the airport continued to see these kinds of delays, then officials should go ahead and start planning construction of a new airport in a different location.[174][175]

The head of the expansion facility management cancelled his contract at the end of June 2019 for unspecified personal reasons.[176] The construction progress at the T2 site remained slow,[177][178] but the topping out of T2 finally took place on 30 July.[179] Final equipment tests took place at the airport over the summer of 2019;[180] with the first tests appearing to have been successful.[181]

On 31 July 2019, construction work at terminal T2 was finished in a record time of only 10 months. Initially planned to cost €200 million, the exploding cost of Berlin Brandenburg Airport as a whole made it necessary to reduce standards and cut the cost of T2 by 50%, to no more than €100 million. The attempts to reduce costs were unsuccessful, as criticised in a report to the supervisory board. Nonetheless, Lütke-Daldrup took the timely completion of terminal T2 as a sign that the problems at BER were coming to an end. Lütke-Daldrup said that he was hopeful that the airport could open as soon as August 2020, two months earlier than currently scheduled.[182] In late July 2019, Lütke-Daldrup stated that, of the more than 11,000 shortcomings reported in March 2019, over 70% had been resolved, including several hundred problems of high priority that would preclude the start of the final TÜV rehearsal.[183] On 1 August 2019 a several-month TÜV rehearsal of BER's technical facilities began, marking the first time that all airport systems have been tested simultaneously.[184]

Renewed checks at T2 yielded serious construction lapses, though. The concrete foundation needed to be partly rebuilt to accommodate technical systems,[185][186] with issues in the wiring arrangement and the ability to withstand sustained usage and heat.[187]

It was also announced that a third terminal is planned to be erected by 2029[188] and that €174 m for payments to advisors was not listed in the balance sheets for 2018.[189] Brandenburg's radio station reported that certain tests that were delayed anew at the end of 2019 were what put the opening date of 2020 into doubt again.[190]

2020

[edit]

In January 2020, union strikes threatened to further delay opening. The union has been fighting for a general working payment to limit competition among ground personnel.[191] By mid-February, the planned opening continued to be doubted upon because 5,000 issues still required rectification and certification by an external inspection company (TÜV) in order to complete construction by the end of the first quarter of 2020. These issues were seen as "grave", meaning that any of them could have caused the inspection company to halt operation.[192][193][194] As of 19 February 2020, 1,000 lapses were still unresolved, 3,300 were being checked by TÜV, and 700 proposed solutions had already been rejected. About 70 issues, including the problem of unapproved screw anchors, still lacked the proper documentation to start working on a solution. Those issues threatened to delay the start of test operations that were scheduled for April 2020.[195] The screw anchor problem was resolved in March.[196]

In early 2020, the airport successfully commenced a volunteer-driven test run of its main functions, including processing at ticket counters.[197] After TÜV approved the emergency and safety systems, the airport received final authority approval on 28 April 2020.[198] Construction work officially ended on 15 May 2020.[199]

Christoph Schaefer was set to become new technical head as a successor to Carsten Wilmsen.[200] The position will remain vacant though due to financial difficulties.[201] It also has been reported that the airport operations company FBB is in imminent financial trouble due to the construction issues and delays as well as the COVID-19 pandemic.[202]

The airport finally received its operating licence in May 2020, allowing an opening date to be set.[1][203][204][205] The local and aviation authorities then gave final approval for the airport to open on 31 October 2020.[2] Plans to bring forward the closure of Tegel to June 2020 in the wake of the COVID-19 pandemic were shelved due to an estimated lack of capacity at Schönefeld's old facilities.[206][207]

From August 2020, the procedure to move all equipment from both current airports to their new facilities commenced.[208]

On 15 October 2020, all test runs of the airport's passenger facilities and procedures, which included thousands of volunteers since spring, concluded successfully after being slightly delayed by the COVID-19 pandemic.[209][210]

After Schönefeld's facilities formally became Terminal 5 of BER ahead on 25 October 2020,[3] all airlines moved from Tegel to BER between 31 October and 8 November 2020.[6] The first flight to land at the new airport was an easyJet special service from Tegel on 31 October 2020, followed shortly after by a Lufthansa special service from Munich.[211] Lufthansa applied a special "Hauptstadtflieger" (capital city flyer) sticker to the aircraft in celebration of the flight.[212] The first departure from the new Terminal 1 was a flight to London–Heathrow on 1 November 2020.[213]

References

[edit]
  1. ^ a b "BER soll am 31. Oktober 2020 öffnen". airliners.de (in German). 29 November 2019.
  2. ^ a b "BER: Luftfahrtbehörde erlaubt Inbetriebnahme am 31. Oktober" [BER: Aviation authority permits commissioning on 31 October]. Berliner Kurier (in German). 1 October 2020. Retrieved 31 October 2020.
  3. ^ a b FBB; DMM (7 September 2020). "Berlin-Schönefeld ist am 25. Oktober 2020 Geschichte" [Berlin-Schoenefeld is history on October 25, 2020]. www.dmm.travel (in German). Retrieved 19 September 2022.
  4. ^ "Construction work at Schönefeld Airport: Upgrading of federal highway B96a, car park P4 closed". Flughafen Berlin Brandenburg GmbH. 15 April 2016. Archived from the original on 28 July 2021. Retrieved 19 September 2022.
  5. ^ Fahrun, Joachim (3 July 2015). "Altes Terminal in Schönefeld bleibt nach BER-Start offen" [Old terminal in Schönefeld to remain open after BER start]. Berliner Morgenpost (in German). Retrieved 26 April 2016.
  6. ^ a b aerotelegraph.com – "Moving schedule" (German) 1 October 2020
  7. ^ Joshua Hammer Reprints (23 July 2015). "How Berlin's Futuristic Airport Became a $6 Billion Embarrassment". Bloomberg.com. Bloomberg.
  8. ^ a b c Eddy, Melissa (7 January 2013). "Mayor to Leave Panel Overseeing Delayed Berlin Airport". The New York Times.
  9. ^ "Interesting Engineering Blunders, Interview with Alfredo Di Mauro". YouTube. Archived from the original on 2016-02-08. Retrieved 30 January 2016.
  10. ^ a b c d "October Launch Scrapped: Berlin Airport Opening Delayed Yet Again". Der Spiegel. 7 January 2013.
  11. ^ a b Amann, Melanie; Scherff, Dyrk (13 January 2013). "Die geheime Mängelliste" [The secret list of defects]. Frankfurter Allgemeine Zeitung (in German).
  12. ^ "Fake engineer made Berlin Airport fire system". The Local Germany. 25 June 2014.
  13. ^ Kurpjuweit, Klaus (25 June 2014). "Ex-Planer Alfredo di Mauro war offenbar Hochstapler". Der Tagesspiegel Online.
  14. ^ Britta Beeger: Flughafen BER – Eine Chronik des Scheiterns. In: faz.net (6. März 2017).
  15. ^ "BBI: Wowereit attends groundbreaking ceremony". City of Berlin. 5 September 2006. Archived from the original on 3 May 2014.
  16. ^ "Two years of construction work on the new Capital Airport BBI: "We are right on schedule"" (Press release). Berliner Flughafen-Gesellschaft mbH. 4 September 2008.
  17. ^ "History: Berlin Brandenburg Airport Willy Brandt". Berliner Flughafen-Gesellschaft mbH. Retrieved 29 July 2014.
  18. ^ "Press Kit" (PDF). Berliner Flughafen-Gesellschaft mbH. Archived from the original (PDF) on 30 July 2014. Retrieved 29 July 2014.
  19. ^ "Infotower". Airport of the future. Berliner Flughafen-Gesellschaft mbH. Archived from the original on 19 August 2011. Retrieved 26 August 2015.
  20. ^ "Infotower" [Infotower]. Erlebnis Flughafen (Airport Experience) (in German). Berliner Flughafen-Gesellschaft mbH. Archived from the original on 29 March 2014. Retrieved 26 August 2015.
  21. ^ Metzner, Thorsten (1 June 2016). "Aus für Infotower und Webcam: Am BER wird bald was abgerissen" [An end for the infotower and webcam: Soon, something will be torn down at BER]. Der Tagesspiegel. Berlin. Retrieved 19 March 2017.
  22. ^ Jacobs, Stefan (3 July 2008). "Start frei für das Terminal". Der Tagesspiegel (in German).
  23. ^ "Berlin's new BBI airport: Topping-out ceremony for the terminal" (Press release). Berliner Flughafen-Gesellschaft mbH. Retrieved 29 July 2014.
  24. ^ Fülling, Thomas (25 June 2010). "BER-Start um mehr als ein halbes Jahr verschoben" [BER launch postponed more than six months]. Berliner Morgenpost (in German). Retrieved 29 July 2014.
  25. ^ "Annual Report 2011" (PDF). Berliner Flughafen-Gesellschaft mbH. p. 14. Archived from the original (PDF) on 30 July 2014. Retrieved 29 July 2014.
  26. ^ "Geheimer Prüfbericht rechnet mit Kontrolleuren ab" [Secret test report settles with inspectors]. Der Spiegel (in German). 12 February 2016.
  27. ^ a b "Ist es richtig, dass Ermittler den BER-Bossen auf die Pelle rücken?" [Is it true that investigators are destroying the management of BER?]. B.Z. (in German). 14 February 2016. Archived from the original on 27 February 2016.
  28. ^ "Mega move to new Berlin Airport begins". The Local. 11 April 2012. Archived from the original on 7 January 2013. Retrieved 19 November 2022.
  29. ^ a b "24 h Airport – Der Flughafenumzug live" [24 h Airport: The Airport Move Live] (Press release) (in German). RBB. 30 April 2012. Archived from the original on 17 February 2013.
  30. ^ "New Berlin Airport Won't Open until March 2013". Der Spiegel. 17 May 2012.
  31. ^ Gubisch, Michael (17 August 2012). "Berlin expects Brandenburg costs to overrun by a third". Flightglobal.
  32. ^ "New Berlin Airport to Finally Open Next October". Spiegel Online. 4 September 2012.
  33. ^ Stampfer, Christian (27 December 2012). "Opening of Berlin Brandenburg International Airport Delayed to 2014". Frequent Business Traveler.
  34. ^ "Berlin airport CEO fired after delays to opening". Yahoo News. Associated Press. 16 January 2013.
  35. ^ "BER-Überraschung: Mehdorn wird Chef des Berliner Flughafens" [BER surprise: Mehdorn is chief of the Berlin airport]. Der Spiegel (in German). 8 March 2013.
  36. ^ "Berlin airport's 2014 opening cancelled again". The Local. 8 January 2014.
  37. ^ "BER öffnet vielleicht erst 2016" [BER may open in 2016]. Berliner Zeitung (in German). 24 February 2014. Archived from the original on 5 January 2016. Retrieved 19 November 2022.
  38. ^ Schacht, Holger (11 August 2014). "Mehdorn verplappert sich: "2017 oder 18"" [Mehdorn flubs it... 2017 or 18!]. Berliner Kurier. Archived from the original on 17 August 2014. Retrieved 11 August 2014.
  39. ^ Metzner, Thorsten (15 June 2016). "Bericht des Untersuchungsausschusses Überall Verfehlungen Das BER-Drama auf über 1000 Seiten" [Report of the control commission: Lapses everywhere, The BER Drama on over 1000 pages]. Der Tagesspiegel Online.
  40. ^ "Neues vom Pannenflughafen: Finden Sie den Fehler auf diesem BER-Foto" [News from the Disaster-airport: Try to find the error in this BER picture]. Bild. 20 June 2016.
  41. ^ "Rechnungshof: Flughafen-Aufsichtsrat mit Fachleuten besetzen" [Court of Auditors: Fill Airport Board with experts]. Die Welt (in German). 15 October 2014.
  42. ^ "Landtag will erneut BER-Sonderausschuss einrichten" [Parliament wants to install new BER Special Commission]. Lausitzer Rundschau (in German). Retrieved 15 October 2014.
  43. ^ Schon, Michael (14 October 2014). "Landtag will weiter über den BER reden" [Parliament wants to talk about the BER]. RBB (in German). Archived from the original on 15 October 2014.
  44. ^ "666 – Number of the Beast". Die Tageszeitung (in German). 18 May 2014.
  45. ^ Wehmeyer, J.C. (1 August 2014). "Raten Sie mal, was am BER jetzt wieder vergessen wurde" [Guess what was forgotten at BER again this time]. Bild (in German).
  46. ^ "Zeitung: Brandschutzanlage am BER undicht" [Newspaper: Fire protection system at BER leaking]. Yahoo! News (in German). 18 May 2014.
  47. ^ "Neuer Chef für Berliner Flughafen gesucht" [Looking for New Chief of Berlin airport]. n-tv (in German). 8 December 2014.
  48. ^ "Hartmut Mehdorn tritt als Airport-Chef zurück" [Hartmut Mehdorn resigns as chief Airport]. Bild (in German). 15 December 2014.
  49. ^ Fritsche, Andreas (15 December 2014). "Scheitern programmiert: Andreas Fritsche ist dennoch überrascht von Mehdorns Rückzug" [Programmed Failure: Andreas Fritsche is still surprised by Mehdorn withdrawal]. Neues Deutschland (in German).
  50. ^ "Flughafen-Chef Mühlenfeld beginnt mit der Arbeit" [Airport chief Mühlenfeld begins work]. RBB (in German). 16 March 2015. Retrieved 21 July 2017.
  51. ^ "The anti-Mehdorn: calm, but without vision". Märkische Allgemeine (in German). Archived from the original on 23 June 2015. Retrieved 23 June 2015.
  52. ^ "BER gibt Such nach Generalplaner auf". Archived from the original on 12 June 2015. Retrieved 12 June 2015.
  53. ^ a b "BER soll Baukosten in 25 Jahren einspielen" [BER to recover construction costs in 25 years]. RBB (in German). 18 March 2015. Archived from the original on 24 March 2015.
  54. ^ "Flughafen-Chef Mühlenfeld beginnt mit der Arbeit" [Airports CEO Mühlenfeld starts working] (in German). Archived from the original on 24 March 2015. Retrieved 21 March 2015.
  55. ^ "Mehdorn legt alle öffentlichen Ämter nieder" [Mehdorn leaves all public offices]. Handelsblatt. Dusseldorf. 20 May 2015.
  56. ^ "Flughafen Berlin-Brandenburg: Michael Müller zum Aufsichtsratschef gewählt" [Michael Müller was elected as a member of the Supervisory Board]. Der Spiegel (in German). 3 July 2015.
  57. ^ "Michael Müller rückt von BER-Geschäftsführung ab" [Michael Müller leaves BER's management]. Der Tagesspiegel (in German). 14 October 2015.
  58. ^ "BER weiter vier Monate hinter dem Zeitplan" [BER Four More Months Behind Schedule]. Neues Deutschland. 15 October 2015.
  59. ^ "Bauarbeiten liegen weiterhin hinter dem Soll zurück" [Construction work remains behind the target]. RBB. 14 October 2015. Archived from the original on 15 October 2015.
  60. ^ Petersen, Lars (15 October 2015). "Wird der Flughafen BER doch erst 2018 eröffnet?". Bild (in German).
  61. ^ Dittmer, Diana (22 April 2016). "BER-Start 2017 "plus vier Wochen"? Müller: Jetzt sind die Behörden dran" [BER start 2017 "plus 4 weeks"? Müller: Authorities must act now] (in German).
  62. ^ "Früherer BER-Manager wegen Fluchtgefahr in U-Haft". Archived from the original on 23 June 2015.
  63. ^ "Korruptionsverdacht: Richter steckt früheren BER-Manager in U-Haft". Der Spiegel. 28 May 2015. Retrieved 3 June 2015.
  64. ^ "Neuer Rückschlag für Großflughafen BER". Die Welt. 7 August 2015. Retrieved 7 August 2015.
  65. ^ "Imtech files for bankruptcy protection in NL—Imtech beantragt in Niederlanden Gläubigerschutz". Die Welt. 11 August 2015. Retrieved 11 August 2015.
  66. ^ Zippert, Hans (7 August 2015). "Drum rettet nur den BER, wer auch denken kann wie er" [BER can only be saved by someone who thinks like BER]. welt.de.
  67. ^ "Schrecken ohne Ende" [Horrors without end]. Neues Deutschland.
  68. ^ "Delius sieht BER-Eröffnungstermin stark gefährdet". Retrieved 15 July 2015.
  69. ^ a b "BER-Manager unter Korruptionsverdacht". Retrieved 16 August 2015.
  70. ^ "Eröffnung Ende 2017 wackelt". Der Tagesspiegel Online.
  71. ^ "Suche abgeschlossen: BER-Generalplaner gefunden". BZ. 24 August 2015. Retrieved 27 August 2015.
  72. ^ "Wie es nach dem Baustopp am BER jetzt weitergeht". 21 September 2015. Retrieved 23 September 2015.
  73. ^ NACHRICHTEN, n-tv. "Baustopp am BER aufgehoben". n-tv.de.
  74. ^ "Teilentwarnung am BER-Terminal – Alert partly lifted concerning BER terminal – shutdown probably won't take so long". Berliner Zeitung. Retrieved 26 September 2015.
  75. ^ "BER-Terminalsperrung könnte in Teilen länger dauern – terminal shutdown could take longer in parts- where ventilators are hanging which weigh 4 instead of 2 tons – in total 5".
  76. ^ "BER-Aufsichtsrat hält an 2017 fest-Wenn es schlecht laufe, finde man in dem neuen Terminal in Schönefeld noch 15 solcher Fehler, vermutete Bretschneider.-Brettschneider assumed that if it goes bad you may find 15 of such failures".
  77. ^ Metzner, Thorsten (29 September 2015). "600 Wände müssen ausgetauscht werden". Der Tagesspiegel (in German).
  78. ^ ONLINE, ZEIT (28 September 2015). "BER: 600 Wände müssen ausgetauscht werden". Die Zeit.
  79. ^ "Berliner Flughäfen steigern 2016 ihre Passagierzahlen um elf Prozent". airliners.de. Berlin. 12 January 2017. Archived from the original on 26 August 2017. Retrieved 19 March 2017.
  80. ^ "BER-Desaster fordert Tegel heraus" [BER disaster challenges Tegel]. abendblatt. 19 March 2016. Archived from the original on 20 December 2016. Retrieved 19 November 2022.
  81. ^ "Wieder wegen Brandschutz: Beim BER klappt mal wieder nichts". bild.de. 6 February 2016.
  82. ^ Mallwitz, Thomas Fülling, Gudrun (7 February 2016). "Neue Spekulationen um BER-Eröffnung". Berliner Morgenpost (in German).{{cite web}}: CS1 maint: multiple names: authors list (link)
  83. ^ Metzner, Thorsten (9 April 2016). "BER liegt acht Monate hinter dem Zeitplan" [BER is 8 months behind schedule]. Tagesspiegel.
  84. ^ "Spätestens im Mai muss eine Einigung zum Brandschutz fallen" [At least in May a decision is needed concerning fire protection (in the underground station)]. Tagesspeigel.
  85. ^ Griggs, Ian (15 April 2016). "Troubled German airport's PR man 'sacked for straight-talking interview'". PRWeek.
  86. ^ "Berliner Pannenflughafen: Zu ehrliches Interview – BER-Pressesprecher gefeuert" [Berlin's Defective Airport: Too Honest Interview – BER Press Spokesman fired]. Der Spiegel. Retrieved 19 March 2017.
  87. ^ Metzner, Thorsten (25 April 2016). "Auflagen gefährden Start des BER" [requirements menace start of BER]. Der Tagesspiegel Online.
  88. ^ "Dieser Brief gefährdet die BER Eröffnung" [This letter endangers the BER opening]. Bild. 25 April 2016.
  89. ^ "Sturzflug am BER" [Does the BER dive?].
  90. ^ "Dieses Loch soll das Brandschutzproblem lösen" [This hole is supposed to solve the fire problem]. 5 May 2016.
  91. ^ Jacobs, Stefan (6 May 2016). "BER bekommt zwei Terrarien für frische Luft" [2 terrariums for fresh air provided]. Der Tagesspiegel Online.
  92. ^ "BER und Deutsche Bahn einigen sich auf Vergleich" [airport and GermanRailways agree on agreement concerning the railway station – no court involved]. Archived from the original on 9 May 2016.
  93. ^ Metzner, Thorsten (26 May 2016). "Notplan für BER-Eröffnung 2017 geplatzt" [BER opening plan for 2017 cancelled]. Der Tagesspiegel Online.
  94. ^ "Und wieder gehen Terminpläne am BER in Rauch auf" [Timetable up in smoke once more]. rbb. Archived from the original on 1 January 2017.
  95. ^ Metzner, Thorsten (10 June 2016). "Behörde sagt Fehlende Unterlagen kann man nicht bearbeiten" [Authority says missing forms cannot be handled]. Der Tagesspiegel Online.
  96. ^ "Geständnis zu Prozessbeginn: Ex-BER-Bereichsleiter nahm Schmiergeld an". n-tv. 23 August 2016.
  97. ^ Metzner, Thorsten (25 August 2016). "BER verpasst nächste Teil-Genehmigung für 2017" [BER misses next part-permission]. Tagesspiegel.
  98. ^ Metzner, Thorsten (6 October 2016). "TU-Professor: Tegel kann nach Start des BER offen bleiben" [Technical univ prof – Tegel may stay open after BER start]. Der Tagesspiegel Online.
  99. ^ "Landrat: Letzte Genehmigung für den BER Ende Januar". Berliner Morgenpost. 9 January 2017.
  100. ^ Metzner, Thorsten (28 January 2017). "Nach Verschiebung des Eröffnungstermins: Letzte Baugenehmigung für den BER erteilt" [After postponement of opening date: Final construction approval issued for BER]. Der Tagesspiegel.
  101. ^ "Vor Aufsichtsratssitzung: Wieder platzt ein Termin am BER" [Ahead of board meeting: another deadline goes bust]. Berliner Zeitung. 27 September 2016.
  102. ^ "Verkehrsausschuss-Chef: BER-Eröffnung nicht vor 2018".
  103. ^ "BER-Chef dämpft Hoffnung auf rasche Eröffnung" [BER head dampens hopes for quick opening]. berliner-zeitung.de.
  104. ^ Metzner, Thorsten (16 October 2016). "BER: Defekte Motoren und veraltete Monitore" [Defunct motors and antique monitors]. Der Tagesspiegel Online.
  105. ^ "Bau des Hauptstadtflughafens – Die Lach- und Sachgeschichten des BER" [The top 5 in weird construction failures].
  106. ^ "Der BER bleibt länger zu, weil die Türen nicht aufgehen" [BER stays closed because the doors will not open]. BZ. 17 January 2017.
  107. ^ "ROUNDUP: Neue Probleme rücken BER-Fertigstellung in die Ferne" [New problems push opening further into the future]. 17 January 2017.
  108. ^ "BER kämpft jetzt mit zu dünnen Wasserrohren und defekten Türen" [BER battles thin water pipes and defective doors].
  109. ^ "Wieder Chaos-Kette – Millionenschaden durch neue BER-Panne befürchtet". bild.de. 24 March 2017.
  110. ^ "BER-Bosse wissen seit 2014, dass bis 2018 nichts fliegt" [BER-Bosses knew since 2014 that nothing would fly until 2018]. bild. 31 March 2017. Retrieved 1 April 2017.
  111. ^ "HauptstadtFlughafen-Ministerium plant Lex BER". Focus. 24 May 2015.
  112. ^ von Bullion, Constanze (23 October 2013). "Verloren in der Entrauchungsmatrix" [Lost in the smoke extractor matrix]. Süddeutsche Zeitung (in German).
  113. ^ "BER: Berliner, wollt ihr ewig bauen?" [Berliners, do you want to build forever?]. web.de. Archived from the original on 15 August 2015. Retrieved 15 August 2015.
  114. ^ "Schon wieder verschoben: Großflughafen BER öffnet wohl frühestens 2018". business insider. 21 December 2015. Retrieved 27 December 2015.
  115. ^ "Was die Eröffnung jetzt noch gefährden kann" [What might still endanger the next opening date – Willy Brandt airport is supposed to open in 2 years]. Wirtschaftswoche. 29 December 2015. Retrieved 29 December 2015.
  116. ^ Metzner, Thorsten (28 December 2016). "Auch Flughafen-Chef Mühlenfeld deutet nun BER-Eröffnung erst für 2018 an" [Airport head Mühlenfeld hints at opening in 2018]. Der Tagesspiegel Online. Retrieved 31 December 2016.
  117. ^ "Chance auf BER-Start 2017 "sehr gering"" [Chances of BER opening in 2017 are "very low"]. Retrieved 31 December 2016.
  118. ^ "BER- Eröffnung erneut verschoben?" [opening delayed anew? 5th shift of opening likely – 16 January 2017 likely to see inking of new 1.1 bio loan]. Retrieved 31 December 2016.
  119. ^ "BER-Eröffnung auf 2018 verschoben". Focus. Retrieved 31 December 2016.
  120. ^ "Ryanairs Marketingchef kurbelt BER-Spekulationen an" [Ryanair marketing head fuels BER speculation]. Archived from the original on 7 September 2016.
  121. ^ "Anders als mit Pfusch ist das nicht zu erklaeren" [It cannot be explained as anything other than a botch].
  122. ^ "Abgeordnetenhaus berät über BER-Chaos" [Berlin's house of representatives reviews BER-chaos]. 25 January 2017.
  123. ^ "Ber kann 2017 engueltig nicht oeffnen" [need to rewire electronic doors].
  124. ^
  125. ^ "Terminplan des Pannenairport – Das muss alles passieren, damit der BER eröffnet wird" [Dateline of the error-ridden airport – this needs to happen so it opens]. 3 April 2016.
  126. ^ Metzner, Thorsten (2 April 2016). "Prognose_zum_neuen_Berliner_Flughafen – Der BER kann erst 2019 starten" [estimate for the airport: it can only open 2019 says Dieter Faulenbach da Costa]. Tagesspiegel.
  127. ^ "Lütke Daldrup soll es nun richten" [Luetke-Daldrup is now supposed to get a grip]. Retrieved 6 March 2017.
  128. ^ "Neuer BER-Flughafenchef Daldrup: "Nicht so viel quatschen"". bild. 6 March 2017. Retrieved 6 March 2017.
  129. ^ "Neuer BER-Chef soll 400.000 Euro Gehalt bekommen" [new BER head supposed to earn 400.000euros per year]. Retrieved 19 March 2017.
  130. ^ "Bretschneider neuer Chefaufseher ('Bretschneider to be new head controller')". Retrieved 17 March 2017.
  131. ^ "Kaum ist der neue BER-Chef im Amt, verschiebt er schon!" [The new BER CEO is hardly in office and is already postponing!]. 7 March 2017.
  132. ^ "Eröffnung des BER möglicherweise erst Anfang 2019". Archived from the original on 26 July 2017. Retrieved 16 July 2017.
  133. ^ "BER-Eröffnung erst 2020?" [Ber opening only 2020].
  134. ^ "BER 2018 geht das Geld aus" [BER runs out of money in 2018].
  135. ^ "Diskussionen um neuen PR-Berater am BER" [Discussions about new PR consultants at BER]. Der Tagesspiegel. 22 May 2017.
  136. ^ "Flughafen BER eröffnet womöglich erst 2021". Berliner Morgenpost. 23 November 2017. Retrieved 24 November 2017.
  137. ^ "Berliner Flughafen erst 2021 fertig?". Frankfurter Allgemeine Zeitung. Retrieved 24 November 2017.
  138. ^ Dittmer, Diana (14 December 2017). "Garantien für den BER kann keiner geben" [Guarantees for BER cannot be given]. n-tv.de.
  139. ^ Gassmann, Michael (18 August 2017). "Was bedeutet das Ende von Air Berlin für den BER?" [What does the end of Air Berlin mean for the BER?]. Die Welt.
  140. ^ Ringelstein, Ronja (20 October 2017). "CDU hat es beim Flughafen TXL jetzt eilig—Die Union diskutiert mit Experten, wie Tegel offen bleiben kann. Zentrale Forderungen: ein Gutachten zur BER-Kapazität und Lärmschutzzonen" [Conservatives are now in a hurry—conservatives discussing with experts how Tegel may remain open. Central demand: an analysis of BER capacity and airplane noise]. tagesspiegel. Retrieved 22 October 2017.
  141. ^ "Noch mehr Mängel am Flughafen BER" [Even more lapses at BER airport]. 22 November 2017. Retrieved 23 November 2017.
  142. ^ "Bezieht der BER-Chef rechtswidrig doppelte Bezüge?" [Is the BER-Boss illegally double-dipping?]. Der Tagesspiegel. 31 January 2018. Retrieved 1 February 2018.
  143. ^ "Kosten explodieren weiter – Eröffnung erneut verschoben –" [costs continue to explode – opening delayed anew]. MZ. 23 February 2018. Retrieved 24 February 2018.
  144. ^ "Kosten für BER übersteigen sieben Milliarden Euro". spiegel. 23 February 2018. Retrieved 24 February 2018.
  145. ^ "Interview with Luetke-Daldrup". youtube. 7 July 2023.
  146. ^ "Hunderte Monitore am BER schon veraltet" [Hundreds of monitors already obsolete]. spiegel. 15 March 2018. Retrieved 16 March 2018.
  147. ^ "Im BER sind bereits 750 Monitore ausgebrannt". rp. 16 March 2018. Retrieved 16 March 2018.
  148. ^ "Faulenbach: BER-Ausbau gefährdet Eröffnung". Retrieved 14 April 2018.
  149. ^ "FLUGHAFEN-BERATER ZWEIFELT AN START DES HAUPTSTADTFLUGHAFENS 2020". verkehrs rundschau. Archived from the original on 16 March 2018. Retrieved 16 March 2018.
  150. ^ "Das Ding wird abgerissen und neu gebaut". welt. Retrieved 17 March 2018.
  151. ^ "BER-laesst-Frustpegel-bei-der-Lufthansa-steigen-" [video board member talks deconstruction – BER lets frustration quota fly at Lufthansa]. ntv. Retrieved 18 March 2018.
  152. ^ Metzner, Thorsten (19 April 2018). "Technikchef Marks verlässt den BER" [Technical chief Marks leaves BER]. Der Tagesspiegel Online. Retrieved 20 April 2018.
  153. ^ "Der Technik-Chef des BER hört auf – und bekommt eine sechsstellige Abfindung" [6-digit compensation for former technical head]. Retrieved 29 April 2018.
  154. ^ Metzner, Thorsten (22 May 2018). "Platz- und Zeitnot: Am BER wird es eng und enger-Neue TÜV-Gutachten, strittige Passagierprognosen, dazu eine Personalie und die Frage nach dem Weiterbetrieb Tegels" [It's turning tighter and tighter around (the) BER – new TUV analysis, diverging passenger number predictions- further lack of time and as well whether Tegel will carry on]. Der Tagesspiegel Online. Retrieved 22 May 2018.
  155. ^ "Keine Betriebssicherheit – BER fällt durch TÜV" [no sustained operation – BER fails TUV test]. Retrieved 21 May 2018.
  156. ^ "Die Mängel-Liste wird immer länger" [List of lapses becomes longer]. Retrieved 3 September 2018.
  157. ^ Metzner, Thorsten (23 May 2018). "CDU zitiert BER-Chef in den Ausschuss 2018-05-22" [CDU invites BER head for commission appearance]. Der Tagesspiegel Online. Retrieved 23 May 2018.
  158. ^ "Verfassungsbeschwerden gegen Nachtflugregelung am BER gescheitert" [objection against nighttime flights failed]. tagesspiegel. 31 July 2018. Retrieved 31 July 2018.
  159. ^ Berlin, Berliner Morgenpost -. (29 June 2018). "Wieso noch ein U-Ausschuss zum BER?" [why's there yet another control commission?]. Retrieved 2 July 2018.
  160. ^ "Zweites BER-Terminal: Ausbau doppelt so teuer wie erwartet?" [secondary terminal: extensian as double as expensive as expected?]. Reisereporter. 25 July 2018. Retrieved 25 July 2018.
  161. ^ "Zech baut zweites BER-Terminal". 18 September 2018. Retrieved 20 September 2018.
  162. ^ "BER-Eröffnung im Oktober 2020? Kannste vergessen!" [BER opening in 2020? Forget about it!]. Tagesspiegel. 3 March 2019. Retrieved 4 March 2019.
  163. ^ Metzner, Thorsten (8 March 2019). "Muss die BER-Eröffnung erneut verschoben werden?". Der Tagesspiegel (in German).
  164. ^ Thorsten Metzner (7 April 2019), 2500 Tage nach der BER-Nichteröffnung (in German), Der Tagesspiegel
  165. ^ Fabricius, Michael (17 April 2019). "Das Monster vom BER ist gezähmt" [the Monster is tamed]. Die Welt.
  166. ^ "BER meldet Durchbruch beim Rauchabzug". Retrieved 31 May 2019.
  167. ^ Tina Friedrich; Boris Hermel; Chris Humbs; Susanne Katharina Opalka (9 May 2019). "Das Problem mit den Dübeln". Tagesschau (in German). Rundfunk Berlin Brandenburg.
  168. ^ "Naechster BER Eroeffnungstermin wackelt" [Yet another opening date is shaky]. Retrieved 10 May 2019.
  169. ^ "Der BER hat Probleme mit Plastikdübeln". 16 April 2019. Retrieved 23 April 2019.
  170. ^ "Neue Zweifel an Eröffnungstermin des Berliner Flughafens" [in case BER demands a single check on each plastic anchor to verify whether the plastic anchors are able to withstand the load. Only if not they are to be exchanged by metal anchors. Then again, there are several thousands of'em]. ZEIT. 10 May 2019.
  171. ^ "Neuer Hauptstadtflughafen BER-Chef kann Eröffnung im Oktober 2020 nicht mehr garantieren". Spiegel. 10 May 2019.
  172. ^ Thorsten Gellner (26 May 2019). "BER: 700 Kilometer Kabel müssen neu verlegt werden". Märkische Allgemeine (in German).
  173. ^ "Schwerer Vorwurf: Verkehrsminister gar nicht an BER-Fertigstellung interessiert?" [strong accusation – minister not interested in airport opening?] (in German). 7 June 2019. Retrieved 8 June 2019.
  174. ^ Bath, Dominik (30 June 2019). "CDU-Politiker empfiehlt Plan B für BER" (in German).
  175. ^ "BER: Senftleben bringt Baustopp und Abriss ins Gespräch". 23 August 2019. Retrieved 27 August 2019.
  176. ^ "BER-Gesellschaft: Manager-Kündigung hat keine Auswirkungen" [Manager goodbye has no delay effect says BER]. hamburger Morgenpost (in German). Archived from the original on 29 June 2019. Retrieved 29 June 2019.
  177. ^ "Bauarbeiten an BER-Terminal offenbar weit hinter Zeitplan" [work at BER terminal is far behind schedule]. rbb (in German). Archived from the original on 2 July 2019. Retrieved 2 July 2019.
  178. ^ "ber-rohbau-zusatzterminal-fertig-schoenefeld.html" (in German). Archived from the original on 2019-07-22. Retrieved 2022-11-19.
  179. ^ "Berlin's new BER airport finally tops out Terminal 2". Deutsche Welle. Retrieved 31 July 2019.
  180. ^ "Prüfungen am Hauptstadtflughafen" [Tests at capital airport]. Der Tagesspiegel Online (in German).
  181. ^ "Erste BER-Generalprobe ist geglückt" (in German). Archived from the original on 30 July 2019. Retrieved 4 August 2019.
  182. ^ Metzner, Thorsten (30 July 2019). "Zweites Terminal in Rekordzeit fertig" (in German). Der Tagesspiegel.
  183. ^ "Start der Generalprobe am BER geplatzt" (in German). Der Tagesspiegel. 31 July 2019.
  184. ^ "Generalprobe für den Flughafen BER startet" (in German). 29 July 2019.
  185. ^ "Terminal 2 des BER muss offenbar teilweise zurückgebaut werden" [Terminal 2 of BER needs to be re-constructed]. FAZ. Retrieved 11 September 2019.
  186. ^ "Baumurks am zusätzlichen BER-Terminal 2" [Construction botch at BER]. Neues Deutschland. Retrieved 11 September 2019. Deficiencies in the electrical system and wiring continued to be found in the main terminal,
  187. ^ Metzner, Thorsten (27 September 2019). "Gravierende Mängel an Kabeln der Sicherheitssysteme" [Serious flaws among security wiring]. Der Tagesspiegel Online. Retrieved 27 September 2019.
  188. ^ "BER-Chef: Terminal 3 soll 2029 in Betrieb gehen" [Ber-head: terminal 3 supposed to be online 2029]. airliners. Retrieved 11 October 2019.
  189. ^ SPIEGEL, Andreas Wassermann, DER (27 September 2019). "Flughafen Berlin-Brandenburg: Hunderte Millionen für Bauberatung beim BER – DER SPIEGEL – Wirtschaft". Der Spiegel.{{cite news}}: CS1 maint: multiple names: authors list (link)
  190. ^ "Berliner Opposition zweifelt an BER-Eröffnungstermin". Archived from the original on 23 November 2019. Retrieved 24 November 2019.
  191. ^ Özgenc, Kayhan (11 February 2020). "Pannenairport BER: Tarif-Streit zwischen Verdi und Dienstleistern am Flughafen gefährdet Eröffnung Ende Oktober" [Collective agreement infighting between Verdi and service firms threatens opening at the end of oct]. Business Insider. Retrieved 11 February 2020.
  192. ^ Fröhlich, Alexander (18 February 2020). "laut-sprecher-kein-kindergeburtstag" [BER speaker says BER opening is no kindergarten birthday party]. Der Tagesspiegel Online. Retrieved 19 February 2020.
  193. ^ "Noch mehr als 5000 Bau-Mängel plagen den Flughafen BER" [BER still plagued by 5,000 construction lapses]. 18 February 2020. Retrieved 19 February 2020.
  194. ^ "Der BER hat noch mehr als 5000 Baumängel" [BER still has 5,000 construction lapses]. 18 February 2020. Retrieved 19 February 2020.
  195. ^ Fröhlich, Alexander (18 February 2020). "Probebetrieb am BER gefährdet" [Test operation at BER at risk]. Der Tagesspiegel Online. Retrieved 19 February 2020.
  196. ^ "BER löst das Dübel-Problem" [BER solves screw anchor problem]. 12 March 2020.
  197. ^ Prößer, Claudius (27 January 2020). "Testtouristen gesucht" [Check-tourists wanted for test-processing]. taz. Retrieved 29 January 2020.
  198. ^ "Landkreis Dahme-Spreewald gibt BER frei" [District of Dahme-Spreewald approves BER]. Retrieved 28 April 2020.
  199. ^ "Wir haben fertig" [we are finished]. t-online (in German). 15 May 2020. Retrieved 17 May 2020.
  200. ^ Metzner, Thorsten (8 July 2020). "BER bekommt neuen Technikchef" [BER got a new technical head]. Tagesspiegel. Retrieved 9 July 2020.
  201. ^ "Posten des BER-Technikchefs bleibt vakant". Der Spiegel. 10 July 2020. Retrieved 12 July 2020.
  202. ^ "Am BER klafft eine neue Finanzlücke". Retrieved 14 July 2020.
  203. ^ Fabricius, Michael (19 March 2020). "Berliner Flughafen BER soll trotz Coronakrise eröffnen" [BER airport opening to stay on track despite corona crisis]. Die Welt (in German). Retrieved 23 May 2020.
  204. ^ "Berlin: New 'BER Airport' to Open on 31 October 2020". berlinspectator.com. 9 December 2019.
  205. ^ "Flughafen Tegel bleibt bis November offen" [Tegel Airport stays open until November]. rbb24.de. 3 June 2020. Archived from the original on 8 November 2020. Retrieved 19 November 2022.
  206. ^ Metzner, Thorsten; During, Rainer W. (2 June 2020). "Aus für Flughafen Berlin-Tegel verzögert sich". Der Tagesspiegel Online.
  207. ^ NACHRICHTEN, n-tv. "Flughafen Tegel bleibt bis Oktober am Netz". n-tv.de.
  208. ^ rbb24.de Archived 2020-10-21 at the Wayback Machine (German) 14 October 2020
  209. ^ rbb24.de Archived 2020-10-18 at the Wayback Machine (German) 15 October 2020
  210. ^ Törne, Lars von (21 July 2020). "400 Komparsen spielen heute BER-Eröffnung". Der Tagesspiegel Online. Retrieved 6 August 2020.
  211. ^ Hackenbruch, Felix; Metzner, Thorsten; Jacobs, Stefan (31 October 2020). "Easyjet landete zuerst: Die Baustelle BER ist endlich ein Flughafen" [Easyjet landed first: The construction site BER is finally an airport]. Der Tagesspiegel (in German). Retrieved 2 November 2020.
  212. ^ Grossmann, Cornelius (31 October 2020). "D-AINZ Lufthansa Airbus A320-271N". Planespotters.net.
  213. ^ maz-online.de (German) 28 August 2020