Jump to content

Baltic states synchronization with UCTE

From Wikipedia, the free encyclopedia

Baltic states synchronization with UCTE grid
Location
CountryLithuania, Latvia, Estonia
General directionnorth-south-north
Ownership information
PartnersLitgrid
Augstsprieguma tīkls
Elering
Construction information
CommissionedFebruary 2025 (expected)
Technical information
Typeoverhead power line, subsea cable
Type of currentHVAC
AC voltage400 kV

Baltic states synchronization with UCTE (also known as Baltic Synchro) is an international electricity transmission infrastructure project to synchronize the three Baltic states (Lithuania, Latvia and Estonia) with the Synchronous grid of Continental Europe (UCTE), managed by ENTSO-E, and leave the IPS/UPS transmission system managed by the BRELL (Belarus, Russia, Estonia, Latvia, Lithuania) agreement.[1] The project is expected to be completed by February 2025.[2]

Importance

[edit]

The electricity systems of Estonia, Latvia and Lithuania were integrated into the IPS/UPS following the Soviet occupation of the Baltic States. IPS/UPS is largely managed centrally by Moscow. The synchronization project will allow the three Baltic States to regain full control of their electricity networks and strengthen energy security.[3][4] According to the European Commission, the synchronization of Baltic States is a political and financial priority and therefore it has allocated more than EUR 1.2 billion towards the funding of the project.[5]

History

[edit]

In 2007 the Prime Ministers of the three Baltic States confirmed their strategic objective to become part of the continental European network.[4] In September 2018 an official application for expansion of the synchronous zone was submitted to ENTSO-E.[6] On 27 May 2019, an agreement was signed for the connection of the Baltic states to the Continental Europe synchronous electric power network operation zone.[6]

Proposals to speed up the process

[edit]

The need for synchronization became more urgent after the Russian invasion of Ukraine in 2022. Lithuanian Prime Minister Ingrida Šimonytė announced that Lithuania is seeking to speed up the process of transition and leave BRELL transmission system before 2025 with expected finalized plan made public by the end of 2023.[7]

On 22 April 2023 a stress test was scheduled in the Baltic states to test the infrastructure and operate for a day outside the IPS/UPS grid.[8] Latvia and Estonia withdrew from testing, while Lithuania successfully conducted the test and concluded that the country is ready to join the Synchronous grid of Continental Europe in 2024.[9] Estonia and Latvia proposed the synchronization with the European grid to be delayed to 2025 due to infrastructure not being ready.[10] President of Lithuania Gitanas Nausėda continued to pressure both Estonia and Latvia to synchronize with continental Europe in 2024, without waiting until 2025.[5] Eventually, the countries agreed to synchronize no later than February 2025.[2]

Withdrawal from BRELL

[edit]

On 16 July 2024, the three Baltic states, represented by their transmission system operators Elering (Estonia), AST (Latvia) and Litgrid (Lithuania), formally notified Russia and Belarus of their decision to withdraw from the BRELL agreement.[11] The agreement will legally expire on 7 February 2025 and the Baltic states will technically disconnect from IPS/UPS on 8 February 2025.[11]

Connections

[edit]

On 9 December 2015, Poland and Lithuania commissioned LitPol Link, which was the first direct connection between the Baltic states and the European grid.[12] In 2018 another proposed link with Poland via the Baltic Sea was announced, called Harmony Link.[13] The total investment planned for the Harmony Link project is around €680 million, of which €493 million will come from the Connecting Europe Facility.[14] The Baltic States also have connections with the Nordic electricity grid via Nordbalt and Estlink.

See also

[edit]

References

[edit]
  1. ^ "Lithuanian president hopes Baltic countries will withdraw from BRELL, synchronize together". baltictimes.com. 24 April 2023. Retrieved 12 August 2023.
  2. ^ a b "Baltic ministers agree to synchronise power grids with Europe by early 2025". lrt.lt. 25 July 2023. Retrieved 25 July 2023.
  3. ^ NATO - The Synchronization of the Baltic States’: Geopolitical Implications on the Baltic Sea Region and Beyond
  4. ^ a b Questions and answers on the synchronisation of the Baltic States' electricity networks with the continental European network (CEN)
  5. ^ a b Lithuania continues attempts to convince colleagues to connect Baltic and European networks faster
  6. ^ a b SYNCHRONISATION WITH EUROPE
  7. ^ "Next year Lithuania will announce when electric power system will be synchronized with West". delfi.lt. 24 November 2022. Retrieved 12 August 2023.
  8. ^ ""Litgrid" pirmą kartą veikė visiškai savarankiškai – atliko izoliuoto darbo bandymą". delfi.lt (in Lithuanian). 22 April 2023. Retrieved 12 August 2023.
  9. ^ ""Litgrid" baigė šalies elektros sistemos izoliuoto darbo bandymą". LRT (in Lithuanian). 22 April 2023. Retrieved 12 August 2023.
  10. ^ Nausėda: tikiuosi, kad Baltijos šalys pasitrauks iš BRELL ir sinchronizuosis kartu
  11. ^ a b "Baltic states give Russia notice of electricity grid switch-off date". LSM. 16 July 2024. Retrieved 16 July 2024.
  12. ^ Russia's Power Grip Over Baltics Ending With Billion-Euro Cables
  13. ^ „Harmony Link“ jungties statyba
  14. ^ "About project – Harmony Link". Retrieved 28 February 2022.