Novovoronezh Nuclear Power Plant II
Novovoronezh Nuclear Power Plant II | |
---|---|
Official name | Нововоронежская АЭС II |
Country | Russia |
Location | Voronezh Oblast |
Coordinates | 51°15′53.964″N 39°12′41.22″E / 51.26499000°N 39.2114500°E |
Status | Operational |
Construction began | Unit 1: 24 June 2008 Unit 2: 12 July 2009 |
Commission date | Unit 1: 27 February 2017 Unit 2: 1 November 2019 |
Construction cost | ₽ 250 billion (2009) – between US$ 6.8 billion and US$ 8.7 billion at 2009 exchange rates |
Owner | Rosenergoatom |
Operator | Rosenergoatom |
Nuclear power station | |
Reactor type | VVER |
Reactor supplier | Atomstroyexport |
Cooling towers | 2 × Natural Draft |
Cooling source | Don River |
Power generation | |
Units operational | 1 × 1180 MW 1 × 1150 MW |
Make and model | VVER-1200/392M (AES-2006) |
Nameplate capacity | 2330 MW |
External links | |
Website | https://rosenergoatom.ru/en/npp/novovoronezh-npp/ |
Commons | Related media on Commons |
Novovoronezh Nuclear Power Plant II (NvNPPII; Russian: Нововоронежская АЭС II [ ]) is a Russian nuclear power plant with two 1200 MW pressurized water reactors (VVER) located in Voronezh Oblast. The power plant is built on the same site as the present Novovoronezh Nuclear Power Plant.
Unit 1 started commercial operation in 2017, and was the first Generation III+ nuclear reactor in the world.[1][2] Unit 2 was connected to the grid in 2019.[3]
History
[edit]In 2006, the Russian government legislated a nuclear expansion plan for 2007–2015. The plan aimed to put two new nuclear reactors into operation each year from 2012. This decision provided impetus for the construction of Novovoronezh II, which had been originally been proposed in 1999.[4]
On 20 June 2007 preparations began at the construction site,[5] and the construction starting ceremony was held on 12 July 2009.[6]
In January 2017 the plant took delivery of a safety instrumentation and control system from Areva NP for installation in its Unit 1.[7]
The first criticality of Unit 2 reactor was achieved on 22 March 2019, with connection to the grid on 1 May 2019.
Description
[edit]The power station will comprise two to four VVER-1200/392M reactors of the AES-2006 type. These reactors are the first of their kind. Unit 1 was planned to be added to the grid in 2012, with the second unit to be added a year later.[6] Cost of the project is between 250 billion Rubles.[8] The city of Novovoronezh is to provide housing for incoming NvNPP II construction workers. In early 2008 the first two apartment blocks were complete and ready to use.[9][10]
Construction of the nuclear power plant is important because the existing Novovoronezh nuclear power plant is a focal point of the energy supply system. The power plant complex provides energy not only to Voronezh Oblast but to Belgorod, Lipetsk and Tambov territories as well.[5]
Reactors
[edit]The Novovoronezh Nuclear Power Plant II has two units:
Unit[11] | Reactor type | Net capacity |
Gross capacity |
Construction started |
Electricity Grid |
Commercial Operation |
Expected shutdown |
---|---|---|---|---|---|---|---|
Novovoronezh II-1[12] | VVER-1200/392M (AES-2006) prototype | 1,114 MW | 1,180 MW | 24 June 2008 | 5 August 2016[13] | 27 February 2017[14] | 2077 |
Novovoronezh II-2[15] | VVER-1200/392M (AES-2006) | 1,114 MW | 1,150 MW | 12 July 2009 | 1 May 2019[16] | 1 November 2019[17] | 2079 |
Service life of the VVER-1200 is 60 years.[18] With extension of operation for 20 years.
See also
[edit]References
[edit]- ^ World Nuclear Performance Report 2018 (Report). World Nuclear Association. August 2018. p. 22. Retrieved 10 July 2019.
- ^ "Russia completes world's first Gen III+ reactor; China to start up five reactors in 2017". Nuclear Energy Insider. 8 February 2017. Retrieved 10 July 2019.
- ^ https://www.rosenergoatom.ru/en/for-journalists/highlights/33323/
- ^ "In Woronesch beginnt 2007 der Bau eines neuen Atom-Kraftwerkes" (in German). RIA Novosti. 30 December 2006. Archived from the original on 2 January 2007. Retrieved 14 July 2009.
- ^ a b "Russland will neuen Energieblock mit Druckwasserreaktor bauen - "Rossijskaja Gaseta"" (in German). RIA Novosti. 21 June 2007. Archived from the original on 16 July 2011. Retrieved 14 July 2009.
- ^ a b "Construction starts at second Novovoronezh-II unit". World Nuclear News. 14 July 2009. Retrieved 16 July 2009.
- ^ "AREVA NP supplies Safety Instrumentation and Control System for Generation 3 Reactor". nuclearpowerdaily.com. 4 January 2017. Retrieved 9 January 2017.
- ^ "На Нововоронежской АЭС завершился этап физического пуска седьмого блока". 28 March 2019.
- ^ The headquarters for the construction of Novovoronezh NPP-2 met on 15 November[permanent dead link ]
- ^ On 14 February Atomenergoproekt started the next stage of Novovoronezh NPP-2 project[permanent dead link ]
- ^ "Russian Federation". Power Reactor Information System. International Atomic Energy Agency (IAEA). 18 March 2013. Retrieved 18 March 2013.
- ^ "Novovoronezh 2-1". PRIS. IAEA. 18 March 2013. Retrieved 18 March 2013.
- ^ "Rosatom State Atomic Energy Corporation ROSATOM global leader in nuclear technologies nuclear energy". www.rosatom.ru. Retrieved 2 November 2019.
- ^ "Росэнергоатом: новейший, самый мощный в России и не имеющий аналогов в мире энергоблок №1 Нововоронежской АЭС-2 сдан в промышленную эксплуатацию". rosenergoatom.ru (in Russian). 28 February 2017. Archived from the original on 1 March 2017. Retrieved 1 March 2017.
- ^ "Novovoronezh 2-2". PRIS. IAEA. 18 March 2013. Retrieved 18 March 2013.
- ^ "Novovoronezh 2 2, Russia". www.world-nuclear.org. Retrieved 2 November 2019.
- ^ "Second Novovoronezh II unit enters commercial operation - World Nuclear News". www.world-nuclear-news.org. Retrieved 2 November 2019.
- ^ "Archived copy" (PDF). Archived from the original (PDF) on 13 March 2017. Retrieved 12 March 2017.
{{cite web}}
: CS1 maint: archived copy as title (link)