Morgan Whyalla pipeline

Coordinates: 34°01′19″S 139°41′10″E / 34.022°S 139.686°E / -34.022; 139.686
From Wikipedia, the free encyclopedia
(Redirected from Morgan–Whyalla pipeline)

Morgan Whyalla pipeline
Pumping Station at Morgan
Pumping Station at Morgan
Map
Map of Morgan Whyalla pipeline
Location
CountryAustralia
StateSouth Australia
Coordinates34°01′19″S 139°41′10″E / 34.022°S 139.686°E / -34.022; 139.686
General directionSoutheast–northwest
FromMorgan
ToWhyalla
General information
Typewater
StatusOperational
OwnerSA Water
OperatorSA Water
Manufacturer of pipesHume Pipe Company
Construction started1940
Commissioned1944
Technical information
Length223 mi (359 km)
Diameter30–21 in (762–533 mm)
No. of pumping stations4
Pumping stationsMorgan, Beatty, Geranium Plains, Robertstown

The Morgan – Whyalla pipeline was an engineering project undertaken by the South Australian Government in 1940 to bring water from Morgan on the River Murray to the industrial city of Whyalla. A second pipeline, by a divergent route, was laid in the 1960s.

History

[edit]

In 1937 Premier of South Australia Richard Butler negotiated with BHP to erect a blast furnace at Whyalla to process iron ore from Iron Knob using brown coal from Leigh Creek. Lack of sufficient fresh water was an obstacle, To this end Butler pushed through enabling legislation and sent engineers to Western Australia to inspect their achievements in above-ground pipelines, notably the Goldfields pipeline engineered by C. Y. O'Connor. In 1938 Premier Thomas Playford increased the demands on BHP, and came to an agreement with Essington Lewis that if the company were to install a tinplate manufacturing plant, the State would supply the water infrastructure. Playford reckoned on the proposed pipeline also supplying the needs of Commonwealth Railways at Port Augusta for their Trans Australian and Adelaide-Port Augusta railway lines. Prime Minister Lyons agreed to help South Australia with a development loan.

In 1939 Lyons died and was replaced by Robert Menzies; shortly after, World War II broke out and Menzies joined with Britain in declaring war on Germany. Under the changed circumstances, Playford renegotiated the deal in terms of shipbuilding rather than tinplate manufacture. In 1940 the Commonwealth Water Agreement Ratification Act was passed, complementary legislation passed through South Australia's parliament[1] and South Australia's Engineering and Water Supply Department was given the task of getting the job done, under considerable pressure from the War Department, and with reduced manpower and materials due to exigencies of wartime. The first stage, from Whyalla to the Baroota Reservoir, was rushed through to help supply water for shipping. The whole route, using continuously welded steel pipe (supplied by Hume Pipe Company), four pumping stations[2] and 127 concrete storage tanks, was completed in 1944,[3] just in time to alleviate a serious drought that had hit the Mid North of South Australia. The pipeline was officially opened by the Governor of South Australia, Sir Malcolm Barclay-Harvey in 1945.

Originally, the only water treatment was filtering at the intake, which could leave the water looking milky due to suspended colloidal clay.[4] Over the years, the treatment processes have improved, with the Morgan Water treatment Plant opened in 1986.[5] In 2016, water from the Morgan treatment plant was judged by the Water Industry Operators Association of Australia as the best tasting tap water in South Australia.[6] Morgan won the award again in 2017.[5] A further upgrade including larger storage and upgraded filtration and disinfection was conducted in 2018.[7]

Description

[edit]

Morgan is a town on the Murray near the point where the river changes its westerly course to almost due south. The pipeline begins at a pumping station 2 miles (3.2 km) upstream from Morgan at the most north-westerly point of the river. Here a large concrete chamber was constructed, the floor of which is below the river's low water level, and the walls of which rise to above the flood level. The chamber is somewhat elliptical in shape and is divided by a wall across the smaller diameter; one half housing the pumps and the other containing the screening machinery. The concrete walls of the chamber are over a metre thick to give it sufficient weight to prevent it floating during a flood. A control room above the chamber houses the switch board, instruments and a diesel stand-by generator.

Water is drawn from the river and passed through rotary screens with a fine wire mesh of 200 openings to the inch (80 per cm). This was originally the only filtration and removed all solid matter except colloidal clay, which when present gave rise to a milky appearance. The water received no other treatment, and its salinity and hardness were less than that of Mundaring water which is used in the comparable Goldfields pipeline. The centrifugal pumps were driven by 400 h.p. (300 kW) electric motors, the power for which was originally supplied from the Osborne Power Station, and later from Port Augusta. Each pump station is now connected directly to the ElectraNet transmission grid. The transformers were upgraded in 2015–2016.[8]

Each pumping station fills receiving tanks elevated by 400 feet (120 m) Each intermediate pump is at a lower elevation than the previous storage tank, so the centrifugal pumps run with a flooded inlet and do not require priming. The last pumping station near Robertstown operates into the Hanson storage tanks, which are 1,558 feet (475 m) above sea level and 57 miles (92 km) from Morgan. From Morgan to No. 4 pumping station the pipe passes through arid country; after that it passes through good agricultural land and thence through the Flinders Ranges at Hughes Gap. The pipe then follows the eastern side of Spencer Gulf to Port Augusta and after rounding the head of the gulf continues southward to Whyalla, again passing through arid country. The route was chosen to pass close to all the main reservoirs in the Mid North of South Australia, so that they could be supplied with River Murray water. From the Hanson tanks the water gravitates all the way to Whyalla, a distance of 166 miles (267 km). The total length of the pipeline is 223 miles (359 km) and the pipes, which are of steel, concrete lined and protected against external corrosion by "galvanite", a proprietary zinc coating, vary in size from 30 inches (760 mm) to 21 inches (530 mm).

The South Australian engineers followed the practice of the Goldfields Water Supply in adopting continuous welding of the pipes. This was soon vindicated when floods hit Port Augusta and Whyalla, causing damage to roads, bridges and the pipeline. At one place, where the water had swept across the road and piled timber up against the pipeline a length of pipe 80 m. between concrete blocks had been bowed outward by over a metre, but had not broken. In another place an 80 m. length of pipe had been completely undermined, and the pipe had sagged about a metre, being dragged down by a large concrete block, weighing about three tonnes, which was left suspended. Close to the block the pipe had buckled, and twisted through 180 degrees without fracture. Two breaks had occurred in the pipeline during the flood, both at places where it was carried over creeks on concrete road bridges. These bridges had been undermined and swept away, carrying the pipe with them. Repairs were made as soon as the flood subsided, and the supply to Whyalla was restored within ten days.[4]

Water from the Morgan water treatment plant supplies over 130,000 people across the Mid North region of South Australia from Burra and Clare, South Australia across to central Eyre Peninsula.[7]

Solar power

[edit]

Commencing in 2019, the pumping stations are being fitted with solar panel arrays to reduce the cost of pumping water. The first of these was commissioned at Pumping Station Number 3 near Geranium Plains. The second will be at Pumping Station number 4 near Robertstown.[9] The ground under the solar panel arrays will be planted with native grasses and ground covers to suppress dust.[10]

[edit]

A second Morgan–Whyalla pipeline was commenced in 1963 and completed in 1967. It was made considerably shorter by passing the last section under Spencer Gulf rather than around it.[citation needed]

A similar project, the Mannum–Adelaide pipeline, began in 1949 and was completed in 1955, just in time to avert a serious water shortage.

See also

[edit]

References

[edit]
  1. ^ "Morgan-Whyalla Pipeline Bill". The Advertiser. Adelaide: National Library of Australia. 23 August 1940. p. 20. Retrieved 29 July 2014.
  2. ^ "Progressive State Move— The Morgan-Whyalla Pipeline". The Mail. Adelaide: National Library of Australia. 31 January 1942. p. 14. Retrieved 29 July 2014.
  3. ^ "Big Undertaking Completed". Daily Advertiser. Wagga Wagga, NSW: National Library of Australia. 1 April 1944. p. 2. Retrieved 29 July 2014.
  4. ^ a b "A Modern Water Scheme". Kalgoorlie Miner. WA: National Library of Australia. 5 April 1946. p. 1. Retrieved 29 July 2014. This article gives a series of interesting comparisons with the somewhat larger Goldfields scheme.
  5. ^ a b Dickers, Jessica (19 July 2017). "Treatment plant wins best tasting water in SA". Pump Industry. Monkey Media. Retrieved 5 January 2021.
  6. ^ "Morgan Water Treatment Plant produces South Australia's top drop". SA Water. 13 July 2016. Retrieved 5 January 2021.
  7. ^ a b "Work starts on $15 million upgrade at Morgan". SA Water. 23 April 2018. Retrieved 5 January 2021.
  8. ^ "SA Water Pump Stations Transformer Replacement" (PDF). ElectraNet. September 2015. Retrieved 13 January 2021.
  9. ^ "Morgan to Whyalla Pipeline powering up with solar". SA Water. 28 August 2019. Retrieved 4 January 2021.
  10. ^ Mayfield, Louis (16 July 2020). "Sunny future for Morgan-Whyalla Pipeline". Whyalla News. Retrieved 13 January 2021.

Sources

[edit]
  • Hammerton, Marianne Water South Australia Wakefield Press, Adelaide 1986 ISBN 0 949268 75 5