Jump to content

Mesochora Dam

Coordinates: 39°27′51.86″N 21°18′15.08″E / 39.4644056°N 21.3041889°E / 39.4644056; 21.3041889
From Wikipedia, the free encyclopedia
(Redirected from Messochora Dam)
Mesochora Dam
Spillway of Mesochora Dam
Mesochora Dam is located in Greece
Mesochora Dam
Location of Mesochora Dam in Greece
CountryGreece
LocationMesochora, Trikala
Coordinates39°27′51.86″N 21°18′15.08″E / 39.4644056°N 21.3041889°E / 39.4644056; 21.3041889
PurposeRiver diversion, irrigation, power
StatusComplete, not commissioned
Construction began1996
Opening date2001
Owner(s)Public Power Corporation of Greece
Dam and spillways
Type of damEmbankment, earth-fill
ImpoundsAcheloos River
Height150 m (490 ft)
Length340 m (1,120 ft)
Dam volume5,000,000 m3 (6,500,000 cu yd)[1]
Reservoir
Total capacity358,000,000 m3 (290,000 acre⋅ft)
Surface area7.8 km2 (3.0 sq mi)
Power Station
TypeConventional
Turbines2 x 81 MW Francis-type (planned)
Installed capacity162 MW (planned)

The Mesochora Dam is concrete-face rock-fill dam on the Acheloos River near Mesochora in Trikala, Greece. The 150 m (490 ft) tall dam is part of the Acheloos River Diversion which is intended to divert a portion of the Acheloos west to irrigate 240,000–380,000 ha (590,000–940,000 acres) in the Thessaly plains. The project includes the Mesochora, Sykia, Mouzaki and Pyli Dams along with a 17.4 km (10.8 mi) long channel.

The idea for an Acheloos to Thessaly diversion project was first envisioned in the 1930s but a lack of funding precluded construction. Interest in the project was revived in 1984 and what was supposed to be a small dam at Mesochora apart from the diversion project was increased in size to support to river diversion. Over the next several years there was a series of legal battles that led to construction stalling, most recently in 2005.[2] Opponents of the scheme cite significant changes to the environment, flooding of villages and that the scheme will divert 600,000,000 m3 (490,000 acre⋅ft) of water annually from the Acheloos. Supporters call on the benefit to the lucrative cotton crops it will help irrigate and the dam's planned 162 MW hydroelectric power plant.[3] The Mesochora Dam was completed in January 2001 but the reservoir has yet to be filled and the power plant has subsequently not been commissioned due to legal battles.[4]

See also

[edit]

References

[edit]
  1. ^ "Large Dams in Greece". Greek Commission on Large Dams. Archived from the original on 21 March 2012. Retrieved 30 April 2013.
  2. ^ "Large Dams in Greece". National Technical University of Athens. Archived from the original on 4 November 2013. Retrieved 30 April 2013.
  3. ^ "Acheloos River Diversion Project, Greece, Greece". Water Technology. Archived from the original on 18 June 2017. Retrieved 30 April 2013.
  4. ^ "Hydroelectric Plants in Greece - Macedonia". IndustCards. Archived from the original on June 15, 2013. Retrieved 30 April 2013.{{cite web}}: CS1 maint: unfit URL (link)
[edit]

Media related to Mesochora Dam at Wikimedia Commons